Department of Public Works

The Cuyahoga County Department of Public Works provides a safe and efficient infrastructure system for residents, employees, businesses, and visitors of Cuyahoga County. The key function of the Public Works Department is to build and maintain public infrastructure and facilities.

Popular Services

bridge iconVeterans Memorial Bridge

Rediscover this landmark through the initiative to reopen its historic streetcar level.

 

 Design/Construction

Access documents & information related to bridge, highway, sanitary, & other construction.

 

 Courthouse Rentals

Facility rentals at the Old Courthouse. Book your wedding or special event!

 

 Sewer Maintenance

Public Works provides maintenance services for sewers throughout the County.

 

Construction Updates

Chagrin River Road - Removal of Bridge over Deer Lick Creek
CONTACTS
Contractor: Northeast OH Trenching Services, Inc.
(216) 440-1768
County: Ryan Maver 216-533-0521
Brian Vigh 216-301-9010
DATES
Start Date: 06-01-2024
Notice To Proceed Date: 06-01-2024
Completion Date:
Scheduled Completion Date: 11-30-2024
Anticipated Completion Date: 11-30-2024
AMOUNTS
Project Amount($):
Contract Award Amount($): 1,574,530.45
Estimated Cost To Completion($):
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

October 4, 2024

Current Zone

  • Two Temporary Fully Actuated Traffic Signals on Miles Rd. and Three Temporary Fully Actuated Traffic Signals on Chagrin River Rd and Sulphur Springs Dr.
  • Phase 2A MOT in place. This includes closure of EB lane on Miles Rd where one way traffic is maintained on WB lane. SB lane on Chagrin Rd is closed and one way traffic is maintained on NB lane. Sulphur Springs Drive is closed for 75 days.

     

    Current Work:

  • Contractor closed Sulphur Springs Drive per 2A phase of the project for 75 allowable days. Sulphur Springs road has been removed for re-alignment. Current work is being done to compact the subgrade, perform cement stabilization, and pave asphalt road base.

     

 

 

September 3, 2024

Current Zone

  • Two temporary fully actuated traffic Signals on Miles Road and three temporary fully actuated traffic signals on Chagrin River Road and Sulphur Springs Drive.
  • Phase 1A MOT in place. This includes closure of WB lane on Miles Road where one way traffic is maintained on EB lane. NB lane on Chagrin Road. is closed and one way traffic is maintained on SB lane.

Current Work:

  • The contractor is working on building the Sulphur Springs extension to Miles Road. This included building subgrade, performing cement stabilization, placing stone and asphalt roadway.
  • New traffic support foundations for the new Miles Road and Sulphur Intersection have been installed.

Chagrin River Road construction    Chagrin River Road construction    Chagrin River Road construction

August 2, 2024

Current Zone

  • Two temporary fully actuated traffic Signals on Miles Road and three temporary fully actuated traffic signals on Chagrin River Road and Sulphur Springs Drive.
  • Phase 1A MOT in place. This includes closure of WB lane on Miles Road where one way traffic is maintained on EB lane. NB lane on Chagrin Road. is closed and one way traffic is maintained on SB lane. < /li>

Current Work:

  • The contractor is working on installing permanent signals on Miles Road for the new intersection placement. They also brought in fill dirt to begin spreading for the new Sulphur Drive extension.

Chagrin River Road construction    Chagrin River Road construction    Chagrin River Road construction