Department of Public Works

The Cuyahoga County Department of Public Works provides a safe and efficient infrastructure system for residents, employees, businesses, and visitors of Cuyahoga County. The key function of the Public Works Department is to build and maintain public infrastructure and facilities.

Popular Services

bridge iconVeterans Memorial Bridge

Rediscover this landmark through the initiative to reopen its historic streetcar level.

 

 Design/Construction

Access documents & information related to bridge, highway, sanitary, & other construction.

 

 Courthouse Rentals

Facility rentals at the Old Courthouse. Book your wedding or special event!

 

 Sewer Maintenance

Public Works provides maintenance services for sewers throughout the County.

 

Construction Updates

Clague Road From Lorain Road to Marion Road
CONTACTS
Contractor: CATTS Construction, Inc.
(440) 998-7871
County: Anne Kiser 440-455-1171
Jon Osterstock
DATES
Start Date: 09-01-2024
Notice To Proceed Date: 09-01-2024
Completion Date:
Scheduled Completion Date: 08-01-2025
Anticipated Completion Date: 08-01-2025
AMOUNTS
Project Amount($):
Contract Award Amount($): 2,479,899.76
Estimated Cost To Completion($): 2,479,899.76
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
PROGRESS

January 8, 2025

  • The detour has been removed and the road is open to traffic.
  • The widening portion of the project is complete.
  • Sidewalk and drive aprons replacement on the west side of the project is complete.
  • Contractor will return in the spring to begin resurfacing the road from Lorain Road to Marion Road.
  • Best management practices (BMP) are in place for erosion control. 

December 3, 2024

Road will open to traffic around mid-December.   All lanes will remain open until Spring when one-way traffic between Lorain Rd. and Marion Rd. will be implemented to complete the project.

  • The chip seal and intermediate paving is complete.
  • Sidewalk and drive aprons replacement on the west side of the project is in progress.
  • This phase of work is anticipated to be completed in late 2024.
  • The road remains closed northbound with a detour route posted.
  • Best management practices (BMP) are in place for erosion control.

 

November 1, 2024

  • The widening phase of Clague Rd. at Maple Ridge Rd. is in progress to install a left turn lane.
  • Sidewalk and drive aprons have been poured on the east side of project.
  • Seeding and mulching is in progress.
  • This phase of work is anticipated to be completed in late 2024.
  • The road remains closed northbound with a detour route posted. • Best management practices (BMP) are in place for erosion control.

 

October 9, 2024

  • The widening phase of Clague Rd. at Maple Ridge Rd. is in process to install a left turn lane.
  • This phase of work is anticipated to be completed late 2024.
  • The road remains closed northbound with a detour route posted.
  • Best management practices (BMP) are in place for erosion control. 

 