Department of Public Works

The Cuyahoga County Department of Public Works provides a safe and efficient infrastructure system for residents, employees, businesses, and visitors of Cuyahoga County. The key function of the Public Works Department is to build and maintain public infrastructure and facilities.

Popular Services

bridge iconVeterans Memorial Bridge

Rediscover this landmark through the initiative to reopen its historic streetcar level.

 

 Design/Construction

Access documents & information related to bridge, highway, sanitary, & other construction.

 

 Courthouse Rentals

Facility rentals at the Old Courthouse. Book your wedding or special event!

 

 Sewer Maintenance

Public Works provides maintenance services for sewers throughout the County.

 

Construction Updates

Hilliard Road - Resurfacing from Riverside Drive to Warren Road
CONTACTS
Contractor: Perk Company, Inc.

County: Darwin Merdes
Mike Cotter 216-280-8757
DATES
Start Date: 06-01-2023
Notice To Proceed Date: 06-01-2023
Completion Date:
Scheduled Completion Date: 12-30-2023
Anticipated Completion Date: 12-30-2023
AMOUNTS
Project Amount($):
Contract Award Amount($): $2,560,100.42
Estimated Cost To Completion($): 0
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
PROGRESS

April 2, 2024

  • Guardrail and sidewalk installation completed.
  • Possibly final striping and signage installation.
  • New plans received from the City of Lakewood in March

February 1, 2024

Project is on winter hiatus.

  • Next spring final striping and signage will be installed. 

December 1, 2023

Work completed in the last weeks.

  • Stamped crosswalks. 
  • Temp striping. Open roadway two-way traffic.
  • Expected in the upcoming weeks will include:
  • Project is on winter hiatus.
  • Next spring final striping and signage will be installed.

November 9, 2023

Work completed in the last weeks.

  • Full depth removal and replacement.
  • Intermediate asphalt paving.
  • ADA ramp and sidewalk removal and replacement.
  • Casting adjustments.
  • Surface asphalt paving.
  • Expected in the upcoming weeks will include:
  • Stamped crosswalks.
  • Temporary striping.
  • Open roadway up to two-way traffic.

October 4, 2023

Work completed in the last weeks.

  • Sanitary and storm sewer replacement
  • Storm structure installation
  • Flipping of traffic
  • Milling
  • Expected in the upcoming weeks will include:
  • Full depth removal and replacement
  • Intermediate asphalt paving
  • ADA ramp and sidewalk removal and replacement
  • Casting adjustments

September 12, 2023

Work completed in the last weeks.

  • ADA ramp and sidewalk replacement.
  • Storm structure installation.
  • Casting adjustments.

     

Expected in the upcoming weeks will include:
  • Storm structure installation.
  • Storm pipe installation.
  • Sanitary pipe installation.

June 14, 2023

  • Start date was delayed due to weather conditions.
  • Traffic zone and milling to begin this week.