Bagley Road's current project zone is from Lindbergh Blvd.to N Rocky River Drive.
The project will be performed in quadrants. Quadrant 1 (south lanes from Lindbergh to N. Rocky River Drive). Quadrant 2 (north lanes from Lindbergh Blvd. to N. Rocky River Drive) will be completed in 2026.
On October 28th the asphalt surface course was placed for Quadrant 1 & 2. In the days that followed, marking subcontractor placed striping/pavement markings in these quadrants and will be opening the road to the original traffic set up, two-way traffic, with two driving lanes in either direction, with a center turn-lane, and with left turn lanes at the intersections.
Throughout the first week of November the contractor will be on site performing hydroseeding for erosion control on the impacted soil/earth behind the north and south curbs of Quadrant 1 & 2.
During this time the contractor will also be removing all construction barrels, navigators/cones, signs and maintenance of traffic devices. Contractor will be demobilized from project site by November 15, 2026.
The N. Rocky Rover Drive to Beech Street portion of the project for the south and north Lanes (Quadrant 3 & 4) will begin work in April of 2027 with an anticipated completion date of August 2027.
Note: This current striping/pavement markings that were placed to open Quadrant 1 & 2 to the original traffic setup (described in the second bullet point) were placed using TEMPORARY striping.
This was done so that upon completion of the project (Quadrants 3 & 4 from N. Rocky River Drive to Beech Street) in 2027 the entire project length (from Lindbergh Blvd. to Beech Street) will receive fresh/new permanent striping at the same time as the project conclusion.
October 1, 2026
Bagley Road's current project zone is from Lindbergh Blvd.to N Rocky River Drive.
Traffic is two-way with single lanes in either direction (with left turn lanes at intersections).
On 9/1 the temporary driving lanes that were on the north side of the existing road (while the zone of work was in the southern lanes) were switched so that the new temporary driving lanes are in the southern lanes (with same two-way traffic described in the initial bullet point above) so work can proceed on the northern lanes.
The project will be performed in quadrants. Now that quadrant one has been paved with intermediate asphalt, work has been on-going quadrant two for the northern lanes from Lindbergh to N. Rocky River Drive. This work has consisted of full depth concrete base repairs and driveway apron/curb replacements.
Additionally, the North Rocky River Bridge has had deck sealing and approach slab repairs in the southern lanes (quadrant one) and northern lanes (quadrant two)
Intermediate asphalt work anticipated to be completed in quadrant two in early October.
The Lindbergh to N. Rocky River Drive portion of the project for the south and north lanes (quadrants one and two) have an anticipated completion of November 15, 2026. Upon completion of this date, the contractor will demobilize from the site and remove the construction sone until Spring 2027.
The N Rocky River Drive to Beech portion of the project for the south and north lanes (quadrants 3 & 4 ) will begin work in April of 2027 with an anticipated completion of August 2027.
September 2, 2026
Bagley Road's current project zone is from Lindbergh Blvd.to N Rocky River Drive.
Traffic is two-way with single lanes in either direction (with left turn lanes at intersections).
On 9/1 the temporary driving lanes are on the north side of the existing road (while the zone of work was in the southern lanes) will be switched so that the new temporary driving lanes will be in the southern lanes (with same two-way traffic described in the initial bullet point above) so work can proceed on the northern lanes.
The project will be performed in quadrants. Now that quadrant one has been paved with intermediate asphalt, work will begin on quadrant two for the northern lanes from Lindbergh to N. Rocky River Drive.
Contractor has performed concrete base pavement repairs, casting adjustments, and intermediate asphalt paving in this quadrant (additionally the North Rocky Rover Bridge has had deck sealing and approach slab repairs in the southern lanes and this work will be repeated in the northern bridge lanes after the traffic switch). After the traffic switch to quadrant 2, milling work will begin in the northern lanes in early September.
Intermediate asphalt work anticipated to be completed in this quadrant 2 in early fall. Surface asphalt work anticipated to be completed in BOTH quadrants shortly after.
The Lindbergh to N Rocky River Drive portion of the project for the south and north lanes (quadrants 1 & 2 ) have an anticipated completion of November 15, 2026. Upon completion of this date, the contractor will be de-mobilized from the site and remove the construction zone until Spring 2027.
The N Rocky River Drive to Beech portion of the project for the south and north lanes (quadrants 3 & 4 ) will begin work in April of 2027 with an anticipated completion of August 2027.
August 4, 2026
Bagley Road's current project zone is from Lindbergh Blvd.to N Rocky River Drive.
Traffic is two-way with single lanes in either direction (with left turn lanes at intersections).
The temporary driving lanes are on the north side of the existing road while the work zone is currently being performed in the Southern lanes.
The project will be performed in quadrants (with the area described above being quadrant 1 and quadrant 2 will be the northern lanes from Lindbergh Blvd. to
N Rocky River Drive).
Contractor performed asphalt milling in this first quadrant and began removing the marked concrete repair locations and concrete replacement has started.
Intermediate asphalt work anticipated to be completed in this quadrant this summer (in addition to N Rocky River bridge deck work).
The Lindbergh Blvd. to N Rocky River Drive portion of the project for the south and north lanes (Quadrants 1 & 2) have an anticipated completion of November 15th 2026.
Upon completion of this date, the contractor will de-mobilize from the site and remove the construction zone until Spring 2027.
The N Rocky River Drive to Beech Street portion of the project for the south and north lanes (Quadrants 3 & 4) will begin work in April of 2027 with an anticipated completion of August 2027.
How could we make it better? Leaving an email can assist us in troubleshooting the issue.
Thank you for your feedback
Your feedback means a lot to us. We use it to improve the experience of all of our users.