Projects and Programs

Euclid Beach Connector Shoreline Improvements
CONTACTS
Contractor: Mark Haynes Construction
(419) 663-3457
County: Ryan Maver
Patrick Lynch 216-527-0203
DATES
Start Date: 05-27-2026
Notice To Proceed Date: 05-11-2026
Completion Date:
Scheduled Completion Date: 11-30-2027
Anticipated Completion Date: 11-30-2027
AMOUNTS
Project Amount($):
Contract Award Amount($): 13,272,331.60
Estimated Cost To Completion($): $13,272,331.60
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

August 3, 2026

Progress:

  • Haynes Construction continues to process existing rubble from shoreline and lakebed between CSO #207.
  • Processed rubble will be utilized for embankment.
  • Haynes Construction began proposed stone revetment from Euclid Beach pier to CSO #206 and began stone revetment between CSO #206 and CSO #207.
  • The contractor excavated trench into lakebed and placed limestone toe stone, core stone, filter stone, and armor stone.

Euclid Beach Connector Construction    Euclid Beach Connector Construction

 

July 15, 2026

Progress:

  • Haynes Construction continues to process existing rubble from shoreline from Euclid Beach pier to NEORSD CSO #206 and between CSO #206 and CSO #207. Processed rubble will be utilized for embankment.
  • Haynes Construction began proposed stone revetment from Euclid Beach pier to CSO #206. The contractor excavated trench into lakebed and placed limestone toe stone, core stone, filter stone, and armor stone.

Euclid Beach Connector construction    Euclid Beach Connector construction

 

July 1, 2026

Progress:

  • Haynes Construction established access road to shoreline, and staging area, at E. 156th Street through NEORSD property.
  • Haynes continued work at NEORSD CSO #206, constructing a ramp over outfall, to access shoreline between CSO #206 and CSO #207.
  • Contractor is scheduled to begin in-water work beginning on July 1st from Euclid Beach Park to CSO #206 and will continue processing existing rubble from lake and shoreline.

 

Progress:

  • Haynes Construction completed staging area and access ramp to shoreline.
  • Haynes Construction continues to crush existing shoreline rubble for use as proposed embankment working east to west from Euclid Beach Park STA 27+50 to NEORSD CSO #207 STA 18+12. The contractor is scheduled to begin in water work on 7-1-26.

 

June 1, 2026

Progress:

  • Haynes Construction performed pre-construction video, as required, prior to mobilizing/beginning construction.
  • Haynes mobilized to project and began construction and stabilization of staging area and access ramp to shoreline in Metroparks Euclid Beach Park.
  • Shoreline work began starting at Euclid Beach Park proceeding east to west scheduled for the week of 6-1-26.

  
How could we make it better? Leaving an email can assist us in troubleshooting the issue.
  
Thank you for your feedback
Your feedback means a lot to us. We use it to improve the experience of all of our users.