Haynes Construction continues to process existing rubble from shoreline and lakebed between CSO #207.
Processed rubble will be utilized for embankment.
Haynes Construction began proposed stone revetment from Euclid Beach pier to CSO #206 and began stone revetment between CSO #206 and CSO #207.
The contractor excavated trench into lakebed and placed limestone toe stone, core stone, filter stone, and armor stone.
July 15, 2026
Progress:
Haynes Construction continues to process existing rubble from shoreline from Euclid Beach pier to NEORSD CSO #206 and between CSO #206 and CSO #207. Processed rubble will be utilized for embankment.
Haynes Construction began proposed stone revetment from Euclid Beach pier to CSO #206. The contractor excavated trench into lakebed and placed limestone toe stone, core stone, filter stone, and armor stone.
July 1, 2026
Progress:
Haynes Construction established access road to shoreline, and staging area, at E. 156th Street through NEORSD property.
Haynes continued work at NEORSD CSO #206, constructing a ramp over outfall, to access shoreline between CSO #206 and CSO #207.
Contractor is scheduled to begin in-water work beginning on July 1st from Euclid Beach Park to CSO #206 and will continue processing existing rubble from lake and shoreline.
Progress:
Haynes Construction completed staging area and access ramp to shoreline.
Haynes Construction continues to crush existing shoreline rubble for use as proposed embankment working east to west from Euclid Beach Park STA 27+50 to NEORSD CSO #207 STA 18+12. The contractor is scheduled to begin in water work on 7-1-26.
June 1, 2026
Progress:
Haynes Construction performed pre-construction video, as required, prior to mobilizing/beginning construction.
Haynes mobilized to project and began construction and stabilization of staging area and access ramp to shoreline in Metroparks Euclid Beach Park.
Shoreline work began starting at Euclid Beach Park proceeding east to west scheduled for the week of 6-1-26.
How could we make it better? Leaving an email can assist us in troubleshooting the issue.
Thank you for your feedback
Your feedback means a lot to us. We use it to improve the experience of all of our users.