This website may be temporarily unavailable on October 10 from 9:00 a.m. to 1:00 p.m. Eastern Time. Thank you for your patience.

Projects and Programs

◄

Lee Road Rehabilitation
CONTACTS
Contractor: Perk Company

County: Ryan Maver
Brian Vigh 216-215-9115
DATES
Start Date: 05-01-2026
Notice To Proceed Date: 09-01-2026
Completion Date:
Scheduled Completion Date: 05-30-2029
Anticipated Completion Date: 05-30-2029
AMOUNTS
Project Amount($):
Contract Award Amount($): 23,917,214.74
Estimated Cost To Completion($): $23,917,214.74
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

October 1, 2026

St. Clair Bridge rehabilitation of existing bridge.

Current Zone

  • Two-Way traffic maintained: Southbound lanes closed from Chagrin Blvd. to Lomond Blvd.
  • Northbound lanes have been changed into two-way traffic; Northbound and southbound traffic.
  • Southbound traffic is being merged from southbound lanes to two-way northbound lanes.
  • Northbound traffic remains in curb lane of two-way northbound lanes.

Current Work

  • Contractors are staging equipment necessary to begin work on the sanitary sewers.
  • Potholding has been performed in the roadway in preparation of the sewer work.

Lee Road Rehabilitation Construction    Lee Road Rehabilitation Construction


  
How could we make it better? Leaving an email can assist us in troubleshooting the issue.
  
Thank you for your feedback
Your feedback means a lot to us. We use it to improve the experience of all of our users.