Projects and Programs
◄
Notice To Proceed Date: 11-01-2023
Completion Date:
Anticipated Completion Date: 05-31-2027
Contract Award Amount($): 28,771,797.70
Estimated Cost To Completion($): $28,771,797.70
Approved Contract Decreases($): 0
August 3, 2026
Work Completed:
- Complete tying deck rebar 09.35.
- Pour 09.35 bridge deck.
- Begin soil anchor installation on 09.68 forward retaining wall.
- Drive rear abutment pile 09.68.
- Form tie and pour 09.68 rear abutment footer and beam seat.
- 09.03 approach slabs formed and poured.
Expected Work:
- Complete forming and pour 09.03 parapet wall.
- 09.35 finish cross frame installation.
- 09.35 closure pour.
- Begin work on 09.35 sleeper slab and approach slab and roadway base.
July 1, 2026
Work Completed:
- False deck bridge 09.35 Phase II.
- Form and pour wingwalls 09.35.
- Drive sheeting and fabricate wailers for retaining wall of 09.68 forward.
- Final grading of 304 base full depth replacement areas of 09.03.
- Form, tie rebar, and pour sleeper and approach slabs of 09.03.
- Shear studs installed on beam line of 09.35.
Expected Work:
- Complete forming and pour 09.03 parapet wall.
- Complete tying deck rebar 09.35.
- Pour 09.35 bridge deck.
- Begin soil anchor installation on 09.68 forward retaining wall.
- Drive rear abutment pile 09.68.
June 8, 2026
Work Completed:
- Project delayed.
May 4, 2026
Work Completed:
- Project delayed due to First Energy with no crews onsite.
Expected Work
- No work is expected until telecom relocations are completed.
April 2, 2026
Work Completed:
- Project delayed due to First Energy with no crews onsite.
- Drainage structure install.
- Full depth removal limits per plan and building up the subbase preparing asphalt.
Expected Work
- No work is expected until telecom relocations are completed.
March 5, 2025
Work Completed:
- Bridge pier demolition.
- General labor crew
- Project was delayed due to First Energy until April 2025.
- Drainage structure install.
Upcoming Work:
- Full depth removal limits per plan and building up the subbase preparing for asphalt.
- General labor crew.
February 4, 2026
Progress
- Bridge over CVSR Phase II steel erection-January 7th & 8th.
- Bridge over Cuyahoga River Phase II demolition in progress.
- Bridge 09.35 drainage completed.
- Full depth pavement removal.
Upcoming Work:
- Bridge pier demolition.
- General labor crew.
- Project delayed due to First Energy until at least March 1st.
January 5, 2026
Work Completed:
- One span remains for bridge over Cuyahoga River Phase II.
- Bridge over CVSR Pier 1 & 2 Pier caps poured.
- Bridge over Riverview Road south parapet framework.
- Bridge over Riverview Road phase line sheeting removed.
- Connector D drainage work.
- Connector D stone subbase completed.
Expected in Upcoming weeks:
- Bridge over Riverview approach slabs.
- Bridge over CVSR Phase II steel erection January 7th-8th
- Bridge over Cuyahoga River Phase II demolition in progress.
December 5, 2025
Work Completed:
- Bridge over Riverview Road
- LSM backfill, waterproofing, and abutment drainage.
- Bridge over CVSR
- Pier II pile driving, road abutments poured, pier footers and Pier II stem poured.
- Halfway through bridge over Cuyahoga Rover Phase II demo.
Expected in Upcoming weeks:
- Connector D Drainage work in progress.
- Bridge over Riverview Phase line sheeting removed.
- Bridge over Riverview approach slabs.
- Bridge over CVSR Phase II steel erection-week of December 15th.
- Bridge over Cuyahoga River Phase II demolition in progress.
November 4, 2025
Work Completed:
- Phase 2A to Phase 2B - Opening Pleasant Valley Road to two-way traffic.
- First bridge over River View Road deck pour and closure pour-10/22.
- First bridge over River View Road steel cross frames installed in closure pour.
- Second Bridge over Cuyahoga Valley Scenic Railroad demolition completed.
- Second bridge over CVSR abutments and piers piling and sheeting.
- Second bridge over CSR abutment footers poured.
- Third bridge over Cuyahoga Valley River deck form removal and cross frames installed.
- Phase II silt fence and construction fence installed per SWPP plan.
Upcoming Work:
- First bridge over River View Road south parapet wall form work.
- First bridge over River View Road backfill.
- First Bridge over River View Road approach slabs.
- Second bridge over CVSR abutment beam seats and pier footers.
- Third bridge over Cuyahoga River rear abutment excavation.
- Third bridge over Cuyahoga River Phase II demolition in progress.
October 3, 2025
Work Completed:
- First bridge over Riverview Road deck poured.
- LSM backfill, and underdrain work.
- Pleasant Valley Road and connector ramps pavement removal, pipe and subbase installation and pavement placed for roadway widening.
- Connector B embankment work completed.
- Guardrail removal along existing roadway.
- Temporary portable concrete barrier wall placed along phase line and north side.
- Permanent seeding is done along north side slopes of roadway and erosion control.
Upcoming Work:
- Phase 2A: 30-day closure to complete 103/25, opening Pleasant Valley Road to two-way traffic.
- North side connector ramps, and south site Fitzwater entrance ramp eastbound onto Alexander Road.
- Canal Road closure 10/6-10/7/25 for cross frame hanging.
- First bridge over Riverview Road south parapet wall formwork.
- Second bridge over CVSR Phase 2 demolition in progress, sheeting, and piledriving.
- Third bridge over Cuyahoga River Phase 2 demolition.
- Lane striping for maintenance of traffic.
September 4, 2025
Work Completed:
- First bridge over Riverview Road in Phase II beams placed.
- Pavement removal between second bridge over Cuyahoga Valley Scenic Railroad – Third bridge over Cuyahoga River.
- Phase I completed asphalt and roadway milling.
- Third bridge over Cuyahoga River north parapet wall poured.
- Temporary portable concrete barrier wall placed along phase line and north side.
- Linear grading, topsoil, and seeding done along north side slopes of roadway.
Upcoming Work:
- Traffic will be switched onto roadway and bridges beginning on Friday 9/5/25 weather permitting. This new traffic pattern will remain eastbound traffic only and will include all four Alexander Road Connector Ramps to be closed leaving no access to or from Canal Road for 30 Days.
- After 30 days, traffic will switch to two-way traffic while opening the 3 connector ramps as follows.
- Connector A-Pleasant Valley Road westbound exit ramp to Canal Road.
- Connector B-Canal Road ramp to enter westbound onto Pleasant Valley Road.
- Connector C-Canal Road to enter eastbound onto Pleasant Valley Road.
- After 30-day closure, Connector D (Pleasant Valley Road. eastbound exit ramp to Canal Road) will remain closed.
Please be advised by the end of summer we will have two-way traffic back on Pleasant Valley Road once we enter Phase II of the project.
August 4, 2025
- 09.03 Phase II pier cap poured.
- 09.03 pier cofferdam sheeting removed and backfilled.
- 09.03 rear and forward abutments poured.
- 09.03 rear and forward embankment work completed, and temporary erosion mats placed.
- 09.35 north parapet wall formed.
- 09.35 north side embankment work in progress.
- Between 09.03 and 09.35 full depth concrete base section poured 304 stone subbase installation.
- 09.68 approach slabs poured, expansion joint installed, and sleeper slabs completed.
- 09.68 rear roadway removal in progress.
- Connector ramps A and B curb installation and subgrade work.
- Underdrain work for connector ramps as well as roadway.
Upcoming Work:
- 09.68 rear roadway removal.
- 09.03 Phase II beams expected the week of 8/5.
- 09.35 embankment finished and seeded.
- 09.68 north parapet wall formed and poured.
- Finish connector ramp island curb.
- 09.35 and 09.68 temporary phase line sheeting removal.
- Phase I asphalt pavement
- Switch to Phase II traffic.
July 8, 2025
- 09.03 pier and rear/forward abutment pile driving completed.
- 09.03 pier column and rear/forward abutment footers concrete pours.
- 09.03 Phase II demolition completed.
- 09.35 approach slabs placed on 6/20/25.
- 09.35 parapet wall formed.
- Roadway base underdrain installation.
- East side of 09.68 and connector ramp roadway undercut and base installation.
- 90.68 Phase IIA beams placed 5/28/25-6/6/25.
- 09.68 and 09.35 LSM abutment backfill, APP.
Upcoming Work:
- Connector ramps A & B curb installation (slip form paver and hand poured).
- Removing phase line sheeting from 09.35 and 09.68.
- 09.68 approach slab installations.
- 09.03 abutment and pier cap pours.
- 09.35 full depth removal to limits.
- 09.35 subbase grading and 304 base installation.
- Paving full depth limits (week of 7/21/25).
May 5, 2025
- 09.68 false decking installation
- 09.68 forward abutment backfilling
- 09.68 shear stud installation
- 09.68 rebar installation
- 09.35 bridge deck poured
- 611 drainage installation and underdrain installation
- Flip eastbound traffic to 09.03 bridge deck to begin Phase II demolition.
- SWPPP work.
Upcoming Work:
- 09.68 rebar installation
- 09.03 Phase II demolition
- 09.03 Phase II excavation and pile driving
- Connector ramp A & B pavement removal, subgrade and underdrain installation.
- 09.35 abutment backfill, sleeper slab and approach slab installation and subgrade installation.
April 2, 2025
- 09.68 bolt installation, testing, tensioning.
- 09.68 false decking installation.
- 09.68 forward abutment backfilling.
- 09.03 parapet wall pour.
- 611 drainage installation and underdrain installation.
- SWPPP work.
Upcoming Work:
- 09.68 false decking installation.
- 09.68 Forward abutment backfilling.
- 09.68 shear stud installation.
- 09.68 rebar installation.
- 09.35 bridge deck pour set for April 9, 2025.
- 611 drainage installation and underdrain installation.
- Flip eastbound traffic to 09.03 deck to begin Phase II demolition (flip set for April 3, 2025)
March 10, 2025
- 09.68 beam setting and erection (with localized closures and full day closures of Canal Road).
- 09.03 parapet wall forming.
- 611 drainage installation and underdrain installation.
- SWPPP work.
- Backfill 09.68 FW abutment and install drainage.
Upcoming Work:
- 09.68 bolt tensions
- 09.68 false decking installation.
- 09.68 forward abutment backfilling.
- 09.35 bridge deck pour (weather permitting).
- 09.03 parapet wall pour.
- 611 drainage installation and underdrain installation.
- 09.03 Parapet wall pour.
- 611 drainage installation and underdrain installation.
February 4, 2025
- 09.68 forward abutment footer formed and poured.
- 09.68 forward abutment wall formed and poured.
- 09.68 steel beams began erecting
- SWPPP work
- Backfill pier II and pull sheeting.
Upcoming Work:
- 09.68 beam setting and erection (with localized and full day closures of Canal Road).
- 09.03 Parapet wall forming.
- 611 drainage installation and underdrain installation.
January 8, 2025
- 09.68 forward abutment pile driving
- SWPPP work
- Sheeting pulled and backfilling around Pier I.
- Revetment system installed.
Upcoming Work:
- 09.68 forward abutment footer and abutment wall formed and poured.
- 09.68 forward abutment rebar tying
- Backfill Pier II and pull sheeting.
December 9, 2024
- 09.68 LSM backfill forward and rear abutments
- 09.35 deck rebar steel tying
- 09.35 deck pour
- 09.68 forward abutment pile driving
- 09.68 excavation of forward abutment
- 09.68 Pier II formed and poured
Upcoming Work:
- 09.68 forward abutment pile driving
- Drainage structure instillation
- 09.68 forward abutment footer and abutment wall formed and poured
- 09.68 forward abutment rebar tying
November 8, 2024
Progress:
- 09.03 & 09.68 LSM backfill forward and rear abutments
- 09.35 embankment back fill and compaction
- 09.35 beam delivery and erection
- 09.68 soil Ancor installation forward abutment
- 09.68 excavation of pier 2 and forward abutment footers
- 09.68 CIP and sheet pile driving forward abutment
- Drainage structure instillation
- 09.68 pier 1 formed and poured
Upcoming Work:
- 09.68 LSM Backfill forward and rear abutments
- 09.35 deck rebar steel tying
- 09.35 deck pour
- 09.68 forward abutment pile driving
- 09.68 excavation of forward abutment
- 09.68 pier 2 formed and poured
October 17, 2024
- Bridge deck pour for Phase I of bridge 09.03
- 09.03 site preparation for LSM backfill on forward and rear abutments
- 09.35 embankment back fill and compaction
- 09.68 excavation of pier 2 and forward abutment footers
- 09.68 sheet pile driving for pier 2 and forward abutment
- 09.68 pile driving for pier 2-footer
Expected in the upcoming weeks:
- 09.03 & 09.35 LSM backfill forward and rear abutments
- 09.35 embankment back fill and compaction
- 09.35 beam delivery and erection
- 09.68 soil anchor installation forward abutment
- 09.68 excavation of forward abutment
- 09.68 CIP and sheet pile driving forward abutment
- Drainage structure instillation
September 11, 2024
- Completed causeway installation and temp access fill for 09.68.
- Excavation of pier footers 09.68.
- Pile driving 09.68 abutment footers and pier footers.
- Underdrain installed for bridge abutments for 09.03 and 09.35.
- Steel workers tying rebar reinforcement for pier columns and pier caps.
- Embankment back fill and compaction.
Expected in the upcoming weeks:
- Excavation of pier footers 09.68.
- Cofferdams and bracing installation for piers of 09.68.
- Embankment back fill and compaction.
- LSM backfill of abutments for bridge 09.03, 09.35.
- Pile driving for CIP piles of bridge 09.68.
- Steel workers tying rebar reinforcement for pier footers, pier caps, and bridge deck.
August 2, 2024
- Cofferdams and bracing installation for piers of 09.68.
- Set steel beams for bridge 09.03.
- Excavation of pier footers 09.68.
- Pile driving 09.68 abutment footers and pier footers.
- Poured 09.35 pier columns and pier caps.
- Steel workers tying rebar reinforcement for pier columns and pier caps.
- Embankment back fill and compaction.
Expected in the upcoming weeks:
- Continuing causeway installation and temporary access fill for 09.68.
- Cofferdams and bracing installation for piers of 09.68.
- Embankment back fill and compaction.
- LSM backfill of abutments for bridge 09.03.
- Pile driving for CIP piles of bridge 09.68.





July 3, 2024
- Cutting and picking beams off 09.68.
- Cofferdams and bracing installation for piers of 09.68.
- Excavation and removal of abutment and piers 09.68.
- Pile driving 09.35 abutment footers and pier footers.
- Poured 09.35 abutments and piers.
- Steel workers tying rebar reinforcement for pier columns and pier caps.
Expected in the upcoming weeks:
- Continuing causeway installation and temporary access fill for 09.68.
- Cofferdams and bracing installation for piers of 09.68.
- Excavation and removal of abutment and piers 09.68.
- Setting steel beams for bridge 09.03.
- LSM backfill of abutments for bridge 09.03.
- Pile driving for CIP piles of bridge 09.68.
- Embankments grading and build out.





June 11, 2024
- Demo Phase I of 09.68.
- Excavation and removal of abutment and piers 09.35
- Cutting and picking beams off 09.35.
- Pile driving 09.35 abutment footers and pier footers.
- Poured 09.35 footers for abutments and piers.
- Steel workers tying rebar reinforcement for footers.
- Access road causeway installation.
Expected in the upcoming weeks:
- Cutting and picking beams off 09.68.
- Cofferdams and bracing installation for piers of 09.68.
- Excavation and removal of abutment and piers 09.68.
- Steel workers tying rebar reinforcement for footers.
- Pile driving for CIP piles of bridge 09.68.
- Pier columns and abutment pour 09.35.







May 1, 2024
- Demo phase I of 09.68
- Poured 09.03 footers for abutments and piers.
- Phase line sheeting for 09.35
- Railroad protection installation
- Iron workers in tying rebar for footers, abutments, piers.
- Pile driving for CIP and H-pile for bridge 09.03
Expected in the upcoming weeks:
- Cutting and picking beams off 09.35
- Pile driving 09.35 abutment footers and pier footers.
- Excavation and removal of abutment and piers 09.35
- Steel workers tying rebar reinforcement for footers.
- Access road causeway installation
- Finish Portage trail installation.
- River closure



April 2, 2024
- Demo Phase I of 09.35
- Pile drive of piles for 09.03 footers
- Excavation and forming of abutment footers 09.03.
- Contractor access road installation
- Concrete for CIP piles
- Concrete placed for forward abutment footer.
- Steel workers tying rebar reinforcement for footers.
Expected in the upcoming weeks:
- Demo 09.68
- Pile driving 09.35.
- Phase line sheeting 09.35.
- Excavating and removal of abutment and piers 09.35.
- Steel workers tying rebar reinforcement for footers.
- Access road installation.
- Finish Portage Trail installation.
January 16, 2024
- Traffic zone has been set up.
- Detour Implementation.
- Temporary signals.
- Erosion control.
- Guardrail removal.
Expected in the upcoming weeks:
- Guardrail removal.
- Erosion control.
- Clearing and grubbing
- Access road installation.
- Portage trail installation.