Rockside Road Bridges Over the Cuyahoga Valley Scenic Railroad
CONTACTS
Contractor: The Ruhlin Company

County: Michael Cotter
Michael Gilbert 330-590-3145
DATES
Start Date: 10-01-2025
Notice To Proceed Date: 09-01-2025
Completion Date:
Scheduled Completion Date: 09-01-2027
Anticipated Completion Date: 11-30-2027
AMOUNTS
Project Amount($):
Contract Award Amount($): 22,456,737.00
Estimated Cost To Completion($): $22,456,737.00
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

August 4, 2026

  • BR. 03.23 (RR ) Phase I shear studs and false decking.
  • BR. 03.23 (RR) Deck formed, tied and poured.
  • BR. 03.23 (RR) FWD & rear abutment underdrain and waterproofing.
  • BR. 03.23 (RR) Approach slab formed, tied and poured.
  • BR. 03.23 (RR) Wingwalls formed, tied, and poured.
  • BR. 03.32 (River) Phase structural steel erection, cross members and skidmore.
  • BR. 03.32 (River) Wingwalls tied and formed.
  • BR. 03.32 (River) Phase I ACB mats installed.
  • Bulkhead retaining wall soil anchor installation.
  • MSE wall excavation for leveling pad.

Work Expected in upcoming weeks:

  • BR.03.23 (RR) Phase I sidewalk formed, tied and poured.
  • BR.03.23 (RR) excavation for grout filled mats.
  • BR.03.32 (River) Phase I shear studs and false decking.
  • BR.03.32 (River) Wingwalls poured.
  • BR.03.32 (River) Shear studs and deck steel placed.
  • BR 03.32 (River) MSE panels erected.

 

July 6, 2026

  • Br. 03.23 (RR) rear and forward diaphragms formed, tied, and poured.
  • Br. 03.23 Phase I beam seats formed, tied and poured.
  • Br .03.23 (RR) Phase I structural steel set, bearings welded and crossed frames.
  • Br. 03.23 (RR) Phase I false decking and sear studs.
  • Br. 03.23 (RR) seismic pedestals formed tied poured.
  • Br. 03.23 (River) Phase I rear and forward abutments formed, tied and poured.
  • Br. 03.23 (River) Phase I Pier II stem and cap formed tied and poured.
  • Br. 03.23 (River) semi-integral diaphragm formed, tied and poured.
  • Br. 03.23 (River) Phase I ACB matting placed.
  • Bulkhead retaining wall soil anchor installation started.

Work Expected in upcoming weeks:

  • Br.03.23 (RR) deck reinforcing steel tied.
  • Br.03.23 (RR) deck formed, tied and poured.
  • Br.03.23 (River) Phase I structural steel erection and cross members.
  • Br.03.23 (River) Phase I shear studs and false decking.
  • Br.03.23 (River) false decking.

 

June 8, 2026

  • Br. 03.23 (RR) Phase I FWD and repair piled dynamic load test/restrike and poured.
  • Br. 03.23 (RR) Phase I FWD abutment footer and beam seat, tied, formed, and poured.
  • Br.03.23 (RR) Phase I rear abutment footer and beam seat, tied, formed and poured.
  • Br. 03.23 (RR) Phase I cap and retrofit tied, formed and poured.
  • Br. 03.32 (River) Bulkhead wall temp access fill sheeting.
  • Br. 03.32 (River) Saw cut and demo at FWD phase line.
  • Br. 03.32 (River) Backfill Phase I rear abutment.
  • Br. 03.32 (River) Phase I FWD abutment and Pier II piled dynamic load test/restrike and poured.
  • Br. 03.32 (River) Phase I FWD abutment and Pier II footers to grade.

Work Expected in upcoming weeks:

  • Br.03.23 (RR) Phase I Structural steel erection.
  • Br.03.32 (River) Phase I FWD abutment and Pier II footers tied, formed and poured.
  • Br. 03.32 (River) Phase I rear and FWD beam seats tied, formed and poured.
  • Br. 03.32 (River) Phase I Pier II stem poured.

 

May 4, 2026

  • Br. 03.23 (RR) Phase I Pier cap demo.
  • Br. 03.23 (RR) Phase I Pier stems formed, tied and poured.
  • Br.03.32 (River) Phase I Pier I restrikes.
  • Br. 03.32 (River) Phase I Pier I piles and footer formed, tied and poured.
  • Br. 03.32 (River) Phase I rear abut formed, tied and poured.
  • Br. 03.32 (River) began Phase I Pier II pile driving.
  • Br. 03.32 (River) east riverbank restoration work.
  • Br. 03.32 (River) bulkhead wall lagging.

Work Expected in upcoming weeks:

  • Br.03.23 (RR) Phase I Pier caps formed, tied and poured.
  • Br.03.32 (River) bulkhead wall soil anchors.
  • Br. 03.32 (River) Phase I stem wall formed, tied and poured.
  • Br. 03.32 (River) Phase I Pier II piles and footer formed, tied and poured.
  • Br. 03.32 (River) Phase I forward abut piles.

 

April 2, 2026

  • Br. 03.23 (RR) Phase I asbestos removal, bridge deck, abutment, and approach slab demolition.
  • Br. 03.23 (RR) Phase I micro piles completed.
  • BR.03.23 (RR) Pre-Phase I footers formed, tied and poured.
  • BR. 03-23 (RR) Pre-phase footer backfill.
  • Completed Phase I bulkhead wall soldiers piles.
  • BR. 03.32 (River) PH 1 Pier I pile driving completed awaiting restrike (4/6/26).
  • Br. 03.32 (River) Ph1 Pier II- footer excavated.

Work Expected in upcoming Weeks

  • BR.03.23 (RR) Phase I Pier stems formed, tied and poured.
  • BR. 03.23 (RR) PH 1 pier cap demolition.
  • Bulkhead wall soil anchors.
  • Br. 03.32 (River) Phase ! Pier II pile driving.

 

March 5, 2026

Progress

  • Railroad bridge Pier II north stem formed, rebar tied and poured.
  • Railroad bridge temporary supports installed.
  • Railroad bridge Pier I south micro piles installed and adjusted to grade.
  • Railroad bridge Pier II south micro piles installation has begun.
  • River bridge 2” asbestos containing material removed from south side.
  • River bridge saw cut transverse and longitudinal cuts for bridge deck removal.
  • River bridge removed bridge deck and structural steel beams for Phase I.
  • Saw cut river bridge Pier I for Phase one demolition.
  • Completed Phase I demolition of river bridge Pier I.
  • Began installation of soldier pile for bulkhead retaining wall work.
  • Closure of Rockside Road Station access drive for bulkhead retaining wall work.
  • Saw cut river bridge Pier 4 for Phase I demolition.
  • Restriping of Phase I MOT centerline.

Work Expected in upcoming Weeks

  • Railroad bridge deck saw cutting and starting of Phase I bridge deck demolition.
  • Railroad bridge completion of micro piles on Pier II south side.
  • Railroad bridge Phase I Pier I & II footers formed, tied and poured.
  • Railroad bridge south side 2” asbestos containing material removal of south side.
  • Continue soldier pile instillation for bulkhead retaining wall.
  • Begin installation of soil anchors for bulkhead retaining wall.
  • Complete river bridge demolition of Pier 4 Phase I removal.

February 4, 2026

Progress

  • Phase I MOT implemented-barrier wall, impact attenuators & signage.
  • Cold patch placed at existing bridge 03.23 rear approach slab.
  • Micro piling Pier II footers on north side.
  • 03.23 Pier II north footer formed, rebar tied and poured.
  • Temporary hard wood railroad crossing installed under bridge 03.23.
  • Temporary access fill under bridge 03.32
  • Installation of temporary guard rail
  • Saw cut bridge 03.32 in preparation for demolition.

Work Expected in upcoming Weeks

  • Erosion control.
  • Continuing installing temporary access fill at bridge 03.32.
  • Removal of existing bulkhead at bridge 03.32
  • Closure of Rockside Road Station Park Drive.
  • Saw cut bridge 03.32 in preparation for demolition.
  • Form, tie and pour 03.23 Pier II stem for temporary support as per plan

January 5, 2026

  • 03.23 pier 1 micropiles
  • 03.23 pier 1 micropile proof test
  • 03.23 pier 1-footer formed, rebar tied and poured
  • 03.23 pier 1 stem formed and rebar tied
  • 03.32 false decking

Work Expected in upcoming Weeks

  • Micro piling at pier 2 footers north side
  • Erosion control
  • Micropile pier 2 proof-test
  • Forming, tying steel, and placing pier 2-footer 03.23

December 5, 2025

  • North side temporary /permanent sidewalk.
  • Linear grading and winter seeding around temp/permanent sidewalk.
  • Excavated for pier footers at bridge over CVSR on north side.
  • Test micro pile completed
  • Erosion control BMPs
  • False decking of bridge over CVSR

Work Expected in upcoming Weeks

  • Micro piling at bridge over Cuyahoga Valley Scenic Railroad pier 1 & 2 footers north side.
  • Erosion control
  • Forming, tying steel, and placing pier 1 footer 03.23,

November 4, 2025

Progress

  • Excavation for north side temporary/permanent sidewalk.
  • Concrete placement for permanent sidewalk.
  • First Bridge over Cuyahoga Valley Scenic Railroad Pier footer excavation.

Work Expected in upcoming Weeks

  • Micro piling at first bridge over Cuyahoga Valley Scenic Railroad.
  • Substructure and temporary support of structure work.
  • Temporary asphalt sidewalk placed along north side.

  
How could we make it better? Leaving an email can assist us in troubleshooting the issue.
  
Thank you for your feedback
Your feedback means a lot to us. We use it to improve the experience of all of our users.