This project includes the rehabilitation of approximately 2.3 miles of Warrensville Center Road from Fairmount Boulevard to Mayfield Road. Work includes base repairs, installation of new intermediate and surface asphalt courses, ADA upgrades, installation of two pedestrian hybrid beacons (Hillbrook and Traymore), and implementation of a road diet with bike lanes from Fairmount to Silsby. Additional improvements include new colored/stamped pedestrian crosswalks.
August 3, 2026
Progress:
Current Work Zone:
Two-way traffic is currently maintained on the east half of Warrensville, from Fairmount Circle to just north of Bayard Road, while construction continues on the west half of the roadway. Drivers should expect minor delays and are advised to use caution when traveling through the work zone.
Expected work in the upcoming weeks:
Casting adjustments.
Partial and full-deep repairs.
ADA ramp installations and curb removals/repairs.
Single-pass chip sealing and intermediate asphalt paving (Cedar Road to Fairmount Blvd.).
Surface course paving and striping (Cedar Road to Bayard Road).
July 1, 2026
Progress:
Work Zone Change-Effective Monday July 6th:
Beginning Monday, July 6th, a new work zone will be established to support continued resurfacing operations.
Two-way traffic (one lane in each direction) will shift to the east half of Warrensville Center Road from Fairmount Circle to just north of Bayard Road, as construction activity transitions to the west half of the roadway.
Drivers should expect minor delays and use caution while moving through the work zone.
Expected work in the upcoming weeks:
Wearing course removal.
Partial and full-depth repairs.
Single pass chip sealing.
Intermediate asphalt paving.
June 1, 2026
Progress:
Current Work Zone:
Two-way traffic (one lane in each direction) on the west half of Warrensville Center Road from Mayfield Road to Cedar Road as construction continues on the east half.
Expected work in the upcoming weeks:
Aggregate chip seal
Intermediate asphalt course
Concrete driveway installation.
Sidewalk/ADA ramp reconstruction.
Landscaping.
Colored and stamped decorative sidewalks (northside of Cedar Road).
Additional Notice:
A new work zone will also be established on the north side of the Warrensville and Cedar Roads intersection, reducing Cedar Road traffic by approximately 50% during the installation of new colored/stamped pedestrian crosswalks.
Expect delays.
May 5, 2026
Progress:
A new work zone will be established in the week of May 11, 2026.
Two-way traffic (one lane in each direction) will shift to the west half of Warrensville Road from Mayfield Road to Cedar Road as construction begins on the east half.
A work zone will also be established on the north side of the Warrensville Road and Cedar Road intersection, reducing Cedar Road traffic by approximately 50% during the installation of new colored/stamped pedestrian crosswalks
Expected work in the upcoming weeks:
Wearing course removal.
Partial and Full depth repairs.
Single pass chip sealing.
Intermediate asphalt paving.
How could we make it better? Leaving an email can assist us in troubleshooting the issue.
Thank you for your feedback
Your feedback means a lot to us. We use it to improve the experience of all of our users.