West 140th Street Resurface Existing Roadway - City of Cleveland
CONTACTS
Contractor: Perk Company, Inc.

County: Craig Nauman
Robert Willis 216-308-2080
DATES
Start Date: 07-01-2026
Notice To Proceed Date: 07-01-2026
Completion Date:
Scheduled Completion Date: 10-31-2026
Anticipated Completion Date: 10-31-2026
AMOUNTS
Project Amount($):
Contract Award Amount($): 4,742,557.06
Estimated Cost To Completion($): $4,742,557.06
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

August 4, 2026

Progress:

  • Asphalt milling.
  • Intermediate paving.
  • ADA and sidewalk.
  • Casting adjustments.

Upcoming Work:

  • Landscaping for east side phase.
  • Flip traffic.
  • Asphalt milling (west side).
  • Intermediate paving (west side).

  
How could we make it better? Leaving an email can assist us in troubleshooting the issue.
  
Thank you for your feedback
Your feedback means a lot to us. We use it to improve the experience of all of our users.