Start Date: 09-01-2024
Notice To Proceed Date: 09-01-2024
Completion Date:
Scheduled Completion Date: 08-01-2025
Anticipated Completion Date: 08-01-2025
Project Amount($):
Contract Award Amount($): 2,479,899.76
Estimated Cost To Completion($): 2,479,899.76
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
January 8, 2025
- The detour has been removed and the road is open to traffic.
- The widening portion of the project is complete.
- Sidewalk and drive aprons replacement on the west side of the project is complete.
- Contractor will return in the spring to begin resurfacing the road from Lorain Road to Marion Road.
- Best management practices (BMP) are in place for erosion control.
December 3, 2024
Road will open to traffic around mid-December. All lanes will remain open until Spring when one-way traffic between Lorain Rd. and Marion Rd. will be implemented to complete the project.
- The chip seal and intermediate paving is complete.
- Sidewalk and drive aprons replacement on the west side of the project is in progress.
- This phase of work is anticipated to be completed in late 2024.
- The road remains closed northbound with a detour route posted.
- Best management practices (BMP) are in place for erosion control.
November 1, 2024
- The widening phase of Clague Rd. at Maple Ridge Rd. is in progress to install a left turn lane.
- Sidewalk and drive aprons have been poured on the east side of project.
- Seeding and mulching is in progress.
- This phase of work is anticipated to be completed in late 2024.
- The road remains closed northbound with a detour route posted.
• Best management practices (BMP) are in place for erosion control.
October 9, 2024
- The widening phase of Clague Rd. at Maple Ridge Rd. is in process to install a left turn lane.
- This phase of work is anticipated to be completed late 2024.
- The road remains closed northbound with a detour route posted.
- Best management practices (BMP) are in place for erosion control.