Construction Updates

East 200th Street
CONTACTS
Contractor: Terrace Construction Co., Inc.

County: Darwin Merdes
Rich Orosz 216-598-9615
DATES
Start Date: 07-01-2024
Notice To Proceed Date: 07-01-2024
Completion Date:
Scheduled Completion Date: 10-31-2025
Anticipated Completion Date: 10-31-2025
AMOUNTS
Project Amount($):
Contract Award Amount($): 7,670,965.81
Estimated Cost To Completion($): $7,670,965.81
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

November 8, 2024

Project Overview:

  • Fall 2024- Installation of a new waterline (6,500 LF). (Phase I & II-5,200LF)
  • Spring 2025: Phase III Waterline-1,200 LF & Rehabilitation and resurfacing of roadway.
  • Current Work Zone:
    • One-way traffic is being maintained in the northbound direction (Mohican to Lakeshore Blvd).
    • A detour for southbound traffic has been posted.

Progress:

  • Phase I Waterline (Shawnee Ave to Tyronne Ave):
    • Completed:  Installation of 2,350’ of new 12” ductile iron pipe watermain, including 8” side street tie-ins, long and short side service connections. 
    • In Progress:  Trench and concrete pavement restorations. 
  • Phase II Waterline (Tyronne Ave to Fuller Ave):
    • Completed:  Installation of 3,000’ of new  8” ductile iron pipe watermain, including 8” side street tie-ins.  Chlorination testing (in progress)
    • Tap in new long side and short side service connections.
    • Removal of temporary by-pass waterline system.
    • Trench and pavement restorations.  Various locations.

October 4, 2024

  • Current Work Zone: One-way traffic is being maintained in the northbound direction (Mohican to Lakeshore Blvd). A detour for southbound traffic has been posted.
  • Phase II construction for the new 8” ductile iron pipe watermain situated along the west side of E. 200th Street from Tyronne Ave. to Ball Ave, is underway-over the course of the next couple of weeks.
  • Removal of the existing watermain and its subsequent replacement with 8” ductile iron piping, including removal/reinstallation tie-ins for side street connections at; Ormiston, Trebec, Monterey, Renwood, Arbor, Naumann E, Naumann W, Pasnow, Nicholas, Merideth, Tracy, Locherie, Newton Morris, Wilmore, Westport, and Ball.
  • Maintenance of traffic and setting of and maintaining temporary bypass.
  • Test and chlorinate newly installed 12” watermain (Phase I); Shawnee to Tyronne.
  • Remove, re-tap and reconnect water service connections; (Phase I); Shawnee to Tyronne
  • Trence and pavement restoration. Various locations.

September 3, 2024

Project Overview

  • Fall 2024- Installation of a new waterline (6,500 LF).
  • 2025- Rehabilitation and resurfacing of roadway.

Progress:

  • Current Work Zone: One-way traffic is being maintained in the northbound direction (Mohican to Lakeshore Blvd). A detour for southbound traffic has been posted.
  • Phase I construction for the new ductile iron pipe watermain situated along the west side of E 200th Street from Shawnee Ave to Tyronne Ave, is underway - over the course of the next couple of weeks:
  • Maintenance of traffic and setting of and maintaining temporary bypass.
  • Removal of the existing watermain and its subsequent replacement with new 12" and 8" ductile iron piping, including removal/reinstallation tie-ins for side street connections at: Shawnee, Murnick, Kewanee, Killdeer, Cherokee, Arrowhead, Muskoka, Lindbergh, Mohawk, Pawnee, and Tyronne.
  • Test and chlorinate the new watermain.
  • Remove, re-tap and reconnect water service connections.
  • Trench and pavement restorations.

August 1, 2024

Project Overview

  • Fall 2024- Installation of a new waterline (6,500 LF).
  • 2025- Rehabilitation and resurfacing of roadway.

Progress:

  • Beginning on July 29, 2024, the first phase of construction will kick off on E. 200th Street stretching from Mohican Avenue to Lakeshore Boulevard.
  • Over the next several weeks, the contractor will set up and install temporary watermain bypass on both the east and west sides of the road.
  • Work will begin on the construction of the new ductile iron watermain along the west side of E. 200th Street (Mohican Avenue to Goller Avenue).


  
How could we make it better? Leaving an email can assist us in troubleshooting the issue.
  
Thank you for your feedback
Your feedback means a lot to us. We use it to improve the experience of all of our users.