Construction Updates

Garfield Boulevard - From Warner Road to Turney Road
CONTACTS
Contractor: Anthony Allega Cement Contractor Inc.

County: Ryan Maver
Pat Lynch (216) 678-8408
DATES
Start Date: 06-01-2024
Notice To Proceed Date: 06-01-2024
Completion Date:
Scheduled Completion Date: 11-30-2024
Anticipated Completion Date: 11-30-2025
AMOUNTS
Project Amount($):
Contract Award Amount($): 4,456,756.61
Estimated Cost To Completion($): $4,456,756.61
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

September 3, 2024

  • Replacement of curb, sidewalk, curb ramps and driveway aprons complete in Phase II.
  • Southside of Garfield Boulevard is complete.
  • Reconstruction of the Garfield Blvd/Warner Rd. Intersection.
  • Removal of pavement, excavation for and installation of proposed storm drainage in Phase I, northside of Garfield Blvd.

August 1, 2024

  • Current work consists of removal and replacement of curb, sidewalk, and curb ramps on the south side of Garfield Blvd.
  • Reconstruction of the Garfield Blvd./Warner Rd. intersection.

July 3, 2024

  • Current work consists of removal and replacement of curb, sidewalk, and curb ramps on the south side of Garfield Blvd.

Garfield Boulevard Construction    Garfield Boulevard Construction



  
How could we make it better?
   Please leave a comment before submitting.
Thank you for your feedback
Your feedback means a lot to us. We use it to improve the experience of all of our users.