Construction Updates

Hickory Hill Pump Station-Village of Mayfield
CONTACTS
Contractor: Triad Engineering Contracting Co.

County: Ryan Maver
Robert Willis 216-515-8326
DATES
Start Date: 09-01-2024
Notice To Proceed Date: 09-01-2024
Completion Date:
Scheduled Completion Date: 05-01-2025
Anticipated Completion Date: 05-01-2025
AMOUNTS
Project Amount($):
Contract Award Amount($): $589,975.00
Estimated Cost To Completion($): $589,975.00
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
PROGRESS

December 3, 2024

Progress

  • Installed all conduits for electrical service and grounding rods.
  • Erected equipment rack
  • Installation of grounding grid
  • Poured concrete generator pad.

Upcoming work

  • Electrical wiring placed -2/2025.
  • Sanitary pumps relocated-2/2025.
  • New fencing placed-2/2025.

 

November 8, 2024

Progress

  • Installed all conduits for electrical service and grounding rods.
  • Erected equipment rack.
  • Installation of grounding grid.
  • Poured concrete generator pad.

Upcoming work

  • Electrical wiring placed.
  • Sanitary pumps relocated.
  • New fencing placed.

 



  
How could we make it better? Leaving an email can assist us in troubleshooting the issue.
  
Thank you for your feedback
Your feedback means a lot to us. We use it to improve the experience of all of our users.