Start Date: 06-01-2023
Notice To Proceed Date: 06-01-2023
Completion Date:
Scheduled Completion Date: 12-30-2023
Anticipated Completion Date: 12-30-2023
Project Amount($):
Contract Award Amount($): $2,560,100.42
Estimated Cost To Completion($): 0
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
April 2, 2024
- Guardrail and sidewalk installation completed.
- Possibly final striping and signage installation.
- New plans received from the City of Lakewood in March
February 1, 2024
Project is on winter hiatus.
- Next spring final striping and signage will be installed.
December 1, 2023
Work completed in the last weeks.
- Stamped crosswalks.
- Temp striping. Open roadway two-way traffic.
- Expected in the upcoming weeks will include:
- Project is on winter hiatus.
- Next spring final striping and signage will be installed.
November 9, 2023
Work completed in the last weeks.
- Full depth removal and replacement.
- Intermediate asphalt paving.
- ADA ramp and sidewalk removal and replacement.
- Casting adjustments.
- Surface asphalt paving.
- Expected in the upcoming weeks will include:
- Stamped crosswalks.
- Temporary striping.
- Open roadway up to two-way traffic.
October 4, 2023
Work completed in the last weeks.
- Sanitary and storm sewer replacement
- Storm structure installation
- Flipping of traffic
- Milling
- Expected in the upcoming weeks will include:
- Full depth removal and replacement
- Intermediate asphalt paving
- ADA ramp and sidewalk removal and replacement
- Casting adjustments
September 12, 2023
Work completed in the last weeks.
- ADA ramp and sidewalk replacement.
- Storm structure installation.
- Casting adjustments.
Expected in the upcoming weeks will include:
- Storm structure installation.
- Storm pipe installation.
- Sanitary pipe installation.
June 14, 2023
- Start date was delayed due to weather conditions.
- Traffic zone and milling to begin this week.