Construction Updates

Hilliard Road - Resurfacing from Riverside Drive to Warren Road
CONTACTS
Contractor: Perk Company, Inc.

County: Darwin Merdes
Mike Cotter 216-280-8757
DATES
Start Date: 06-01-2023
Notice To Proceed Date: 06-01-2023
Completion Date:
Scheduled Completion Date: 12-30-2023
Anticipated Completion Date: 12-30-2023
AMOUNTS
Project Amount($):
Contract Award Amount($): $2,560,100.42
Estimated Cost To Completion($): 0
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
PROGRESS

April 2, 2024

  • Guardrail and sidewalk installation completed.
  • Possibly final striping and signage installation.
  • New plans received from the City of Lakewood in March

February 1, 2024

Project is on winter hiatus.

  • Next spring final striping and signage will be installed. 

December 1, 2023

Work completed in the last weeks.

  • Stamped crosswalks. 
  • Temp striping. Open roadway two-way traffic.
  • Expected in the upcoming weeks will include:
  • Project is on winter hiatus.
  • Next spring final striping and signage will be installed.

November 9, 2023

Work completed in the last weeks.

  • Full depth removal and replacement.
  • Intermediate asphalt paving.
  • ADA ramp and sidewalk removal and replacement.
  • Casting adjustments.
  • Surface asphalt paving.
  • Expected in the upcoming weeks will include:
  • Stamped crosswalks.
  • Temporary striping.
  • Open roadway up to two-way traffic.

October 4, 2023

Work completed in the last weeks.

  • Sanitary and storm sewer replacement
  • Storm structure installation
  • Flipping of traffic
  • Milling
  • Expected in the upcoming weeks will include:
  • Full depth removal and replacement
  • Intermediate asphalt paving
  • ADA ramp and sidewalk removal and replacement
  • Casting adjustments

September 12, 2023

Work completed in the last weeks.

  • ADA ramp and sidewalk replacement.
  • Storm structure installation.
  • Casting adjustments.

     

Expected in the upcoming weeks will include:
  • Storm structure installation.
  • Storm pipe installation.
  • Sanitary pipe installation.

June 14, 2023

  • Start date was delayed due to weather conditions.
  • Traffic zone and milling to begin this week.