Construction Updates

Jefferson Avenue Bridge
CONTACTS
Contractor: Schirmer Construction, LLC

County: Darwin Merdes
Josh Banaszak 440-668-4678
DATES
Start Date: 10-01-2024
Notice To Proceed Date: 10-01-2024
Completion Date:
Scheduled Completion Date: 08-01-2025
Anticipated Completion Date: 08-01-2025
AMOUNTS
Project Amount($):
Contract Award Amount($): $4,749,202.00
Estimated Cost To Completion($): $7,749,202.00
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

December 9, 2024

  • Contractor is nearing completion of temporary ramp/roadway work to serve as the project detour.
  • The existing Jefferson Avenue bridge is still open to traffic.
  • Traffic switch (closing Jefferson Bridge and opening temporary detour ramp/route) is expected to occur within one month's time.