Construction Updates

North Marginal Road Connector Shared Use Path from E. 9th Street
CONTACTS
Contractor: Independence Excavating, Inc.

County: Joshua A. Banaszak 440-668-4678
DATES
Start Date: 08-01-2024
Notice To Proceed Date: 08-01-2024
Completion Date:
Scheduled Completion Date: 08-31-2026
Anticipated Completion Date: 08-31-2026
AMOUNTS
Project Amount($):
Contract Award Amount($): 10,812,068.09
Estimated Cost To Completion($): $10,812,068.09
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

December 3, 2024

  • Independence Excavating coordinated/performed initial; pre-phase construction work to allow utility companies (CEI and CPP) to have enough room to perform their relocation work for utility poles/lines.
  • Initial tree removal and clearing and grubbing occurred at various locations during the length of the project.
  • Sections of pavement were cut and removed near the existing curb lines to accommodate new pole locations (minimal pavement removed so two-way traffic is still maintained).
  • Pre-phase work shown above was complete in mid-November.
  • Independence Excavating will be off-site till February 2025 to allow utility companies to have the winter to start/finish their utility pole/lines relocation work.
  • Remaining stump removal for the tree clearing work will continue once the contractor returns to the project site upon the completion of utility relocation work.

October 21, 2024

  • No official construction work has begun for this project.
  • Pre-construction video was recorded for the project earlier this month.
  • The contractor is currently waiting for electrical utility coordination (CPP & CEI) before finalizing the construction schedule.


  
How could we make it better? Leaving an email can assist us in troubleshooting the issue.
  
Thank you for your feedback
Your feedback means a lot to us. We use it to improve the experience of all of our users.