Start Date: 11-01-2023
Notice To Proceed Date: 11-01-2023
Completion Date:
Scheduled Completion Date: 11-01-2026
Anticipated Completion Date: 11-01-2026
Project Amount($): $28,771,797.70
Contract Award Amount($): $28,771,797.70
Estimated Cost To Completion($): 0
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
November 8, 2024
Progress:
- 09.03 & 09.68 LSM backfill forward and rear abutments
- 09.35 embankment back fill and compaction
- 09.35 beam delivery and erection
- 09.68 soil Ancor installation forward abutment
- 09.68 excavation of pier 2 and forward abutment footers
- 09.68 CIP and sheet pile driving forward abutment
- Drainage structure instillation
- 09.68 pier 1 formed and poured
Upcoming Work:
- 09.68 LSM Backfill forward and rear abutments
- 09.35 deck rebar steel tying
- 09.35 deck pour
- 09.68 forward abutment pile driving
- 09.68 excavation of forward abutment
- 09.68 pier 2 formed and poured
October 17, 2024
- Bridge deck pour for Phase I of bridge 09.03
- 09.03 site preparation for LSM backfill on forward and rear abutments
- 09.35 embankment back fill and compaction
- 09.68 excavation of pier 2 and forward abutment footers
- 09.68 sheet pile driving for pier 2 and forward abutment
- 09.68 pile driving for pier 2-footer
Expected in the upcoming weeks:
- 09.03 & 09.35 LSM backfill forward and rear abutments
- 09.35 embankment back fill and compaction
- 09.35 beam delivery and erection
- 09.68 soil anchor installation forward abutment
- 09.68 excavation of forward abutment
- 09.68 CIP and sheet pile driving forward abutment
- Drainage structure instillation
September 11, 2024
- Completed causeway installation and temp access fill for 09.68.
- Excavation of pier footers 09.68.
- Pile driving 09.68 abutment footers and pier footers.
- Underdrain installed for bridge abutments for 09.03 and 09.35.
- Steel workers tying rebar reinforcement for pier columns and pier caps.
- Embankment back fill and compaction.
Expected in the upcoming weeks:
- Excavation of pier footers 09.68.
- Cofferdams and bracing installation for piers of 09.68.
- Embankment back fill and compaction.
- LSM backfill of abutments for bridge 09.03, 09.35.
- Pile driving for CIP piles of bridge 09.68.
- Steel workers tying rebar reinforcement for pier footers, pier caps, and bridge deck.
August 2, 2024
July 3, 2024
- Excavation and removal of abutment and piers 09.68.
- Setting steel beams for bridge 09.03.
- LSM backfill of abutments for bridge 09.03.
- Pile driving for CIP piles of bridge 09.68.
- Embankments grading and build out.
June 11, 2024
- Demo Phase I of 09.68.
- Excavation and removal of abutment and piers 09.35
- Cutting and picking beams off 09.35.
- Pile driving 09.35 abutment footers and pier footers.
- Poured 09.35 footers for abutments and piers.
- Steel workers tying rebar reinforcement for footers.
- Access road causeway installation.
Expected in the upcoming weeks:
- Cutting and picking beams off 09.68.
- Cofferdams and bracing installation for piers of 09.68.
- Excavation and removal of abutment and piers 09.68.
- Steel workers tying rebar reinforcement for footers.
- Pile driving for CIP piles of bridge 09.68.
- Pier columns and abutment pour 09.35.
May 1, 2024
April 2, 2024
January 16, 2024