Construction Updates

Pleasant Valley Road Bridges - City of Independence & Village of Valley View
CONTACTS
Contractor: The Ruhlin Company

County: Matt Cotter 216-280-8757
John Osterstock
DATES
Start Date: 11-01-2023
Notice To Proceed Date: 11-01-2023
Completion Date:
Scheduled Completion Date: 11-01-2026
Anticipated Completion Date: 11-01-2026
AMOUNTS
Project Amount($): $28,771,797.70
Contract Award Amount($): $28,771,797.70
Estimated Cost To Completion($): 0
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
PROGRESS

November 8, 2024

Progress:

  • 09.03 & 09.68 LSM backfill forward and rear abutments
  • 09.35 embankment back fill and compaction
  • 09.35 beam delivery and erection
  • 09.68 soil Ancor installation forward abutment
  • 09.68 excavation of  pier 2 and forward abutment footers
  • 09.68 CIP and sheet pile driving forward abutment
  • Drainage structure instillation
  • 09.68 pier 1 formed and poured

Upcoming Work:

  • 09.68 LSM Backfill forward and rear abutments
  • 09.35 deck rebar steel tying
  • 09.35 deck pour
  • 09.68 forward abutment pile driving
  • 09.68 excavation of forward abutment
  • 09.68 pier 2 formed and poured

October 17, 2024

  • Bridge deck pour for Phase I of bridge 09.03
  • 09.03 site preparation for LSM backfill on forward and rear abutments
  • 09.35 embankment back fill and compaction
  • 09.68 excavation of pier 2 and forward abutment footers
  • 09.68 sheet pile driving for pier 2 and forward abutment
  • 09.68 pile driving for pier 2-footer

Expected in the upcoming weeks:

  • 09.03 & 09.35 LSM backfill forward and rear abutments
  • 09.35 embankment back fill and compaction
  • 09.35 beam delivery and erection
  • 09.68 soil anchor installation forward abutment
  • 09.68 excavation of forward abutment
  • 09.68 CIP and sheet pile driving forward abutment
  • Drainage structure instillation

 

September 11, 2024

  • Completed causeway installation and temp access fill for 09.68.
  • Excavation of pier footers 09.68.
  • Pile driving 09.68 abutment footers and pier footers.
  • Underdrain installed for bridge abutments for 09.03 and 09.35.
  • Steel workers tying rebar reinforcement for pier columns and pier caps.
  • Embankment back fill and compaction.

Expected in the upcoming weeks:

  • Excavation of pier footers 09.68.
  • Cofferdams and bracing installation for piers of 09.68.
  • Embankment back fill and compaction.
  • LSM backfill of abutments for bridge 09.03, 09.35.
  • Pile driving for CIP piles of bridge 09.68.
  • Steel workers tying rebar reinforcement for pier footers, pier caps, and bridge deck.

 

August 2, 2024

  • Cofferdams and bracing installation for piers of 09.68.
  • Set steel beams for bridge 09.03.
  • Excavation of pier footers 09.68.
  • Pile driving 09.68 abutment footers and pier footers.
  • Poured 09.35 pier columns and pier caps.
  • Steel workers tying rebar reinforcement for pier columns and pier caps.
  • Embankment back fill and compaction.


    Expected in the upcoming weeks:

  • Continuing causeway installation and temporary access fill for 09.68.
  • Cofferdams and bracing installation for piers of 09.68.
  • Embankment back fill and compaction.
  • LSM backfill of abutments for bridge 09.03.
  • Pile driving for CIP piles of bridge 09.68.

Pleasant Valley Road Bridge construction    Pleasant Valley Road Bridge construction    Pleasant Valley Road Bridge construction    Pleasant Valley Road Bridge construction    Pleasant Valley Road Bridge construction

July 3, 2024

  • Cutting and picking beams off 09.68.
  • Cofferdams and bracing installation for piers of 09.68.
  • Excavation and removal of abutment and piers 09.68.
  • Pile driving 09.35 abutment footers and pier footers.
  • Poured 09.35 abutments and piers.
  • Steel workers tying rebar reinforcement for pier columns and pier caps.

     

    Expected in the upcoming weeks:

  • Continuing causeway installation and temporary access fill for 09.68.
  • Cofferdams and bracing installation for piers of 09.68.
  • Excavation and removal of abutment and piers 09.68.
  • Setting steel beams for bridge 09.03.
  • LSM backfill of abutments for bridge 09.03.
  • Pile driving for CIP piles of bridge 09.68.
  • Embankments grading and build out.  
       

 

June 11, 2024

  • Demo Phase I of 09.68.
  • Excavation and removal of abutment and piers 09.35
  • Cutting and picking beams off 09.35.
  • Pile driving 09.35 abutment footers and pier footers.
  • Poured 09.35 footers for abutments and piers.
  • Steel workers tying rebar reinforcement for footers.
  • Access road causeway installation.

 

Expected in the upcoming weeks:

  • Cutting and picking beams off 09.68.
  • Cofferdams and bracing installation for piers of 09.68.
  • Excavation and removal of abutment and piers 09.68.
  • Steel workers tying rebar reinforcement for footers.
  • Pile driving for CIP piles of bridge 09.68.
  • Pier columns and abutment pour 09.35.

     

         

May 1, 2024

  • Demo phase I of 09.68
  • Poured 09.03 footers for abutments and piers.
  • Phase line sheeting for 09.35
  • Railroad protection installation
  • Iron workers in tying rebar for footers, abutments, piers.
  • Pile driving for CIP and H-pile for bridge 09.03

     

    Expected in the upcoming weeks:

  • Cutting and picking beams off 09.35
  • Pile driving 09.35 abutment footers and pier footers.
  • Excavation and removal of abutment and piers 09.35
  • Steel workers tying rebar reinforcement for footers.
  • Access road causeway installation Finish Portage trail installation.
  • River closure

Pleasant Valley Bridge construction    Pleasant Valley Bridge construction    Pleasant Valley Bridge construction

April 2, 2024

  • Demo Phase I of 09.35
  • Pile drive of piles for 09.03 footers
  • Excavation and forming of abutment footers 09.03.
  • Contractor access road installation
  • Concrete for CIP piles
  • Concrete placed for forward abutment footer.
  • Steel workers tying rebar reinforcement for footers.

     

    Expected in the upcoming weeks:

  • Demo 09.68
  • Pile driving 09.35.
  • Phase line sheeting 09.35.
  • Excavating and removal of abutment and piers 09.35.
  • Steel workers tying rebar reinforcement for footers.
  • Access road installation.
  • Finish Portage Trail installation.

 

January 16, 2024

  • Traffic zone has been set up.
  • Detour Implementation.
  • Temporary signals.
  • Erosion control.
  • Guardrail removal.

     

    Expected in the upcoming weeks:

  • Guardrail removal.
  • Erosion control.
  • Clearing and grubbing
  • Access road installation.
  • Portage trail installation.

 



  
How could we make it better? Leaving an email can assist us in troubleshooting the issue.
  
Thank you for your feedback
Your feedback means a lot to us. We use it to improve the experience of all of our users.