Start Date: 03-01-2026
Notice To Proceed Date: 03-01-2026
Completion Date:
Scheduled Completion Date: 11-30-2026
Anticipated Completion Date: 11-30-2026
Project Amount($):
Contract Award Amount($): $2,316,572.50
Estimated Cost To Completion($): $2,316,572.50
Approved Contract Increases($):
Approved Contract Decreases($):
September 2, 2026
- Formed, tied rebar, and poured moment slab with concrete.
- Formed, tied rebar, and poured sidewalk with concrete.
- Formed and poured concrete curbs.
- Formed, tied rebar, and poured bridge parapets with concrete and installed tubular railing.
- Installed curb plates along edges of sidewalk.
- Installed roadway underdrain and drainage structures.
- Installed roadway aggregates and asphalt.
- MGS guardrail installed.
Expected in the upcoming weeks:
- Bridge opening back up to two-way traffic.
- Reinstall residential driveway aprons.
- Painting architectural treatment along sides of parapets after concrete curing completes.
- Lane striping and signage reinstalled.
- Detour signage removed.
- Topsoil, seeding and mulching.
August 4, 2026
- Erected Precast arches, headwall, & wingwalls.
- Waterproofed, grouted, and installed drainage within bridge structure.
- Installed Structural Backfill for the precast sections.
- Embankment installed to limits of roadway grade.
- Additional Rock Channel Protection was installed along corners of the structure.
- Painted Precast sections with elastomeric protective and decorative coating.
- Removed temporary shoring walls to grade.
Expected in the upcoming weeks:
- Form, tie rebar, and pour moment slab with concrete.
- Form, tie rebar, and pour sidewalk with concrete.
- Form, tie rebar, and pour bridge parapets with concrete and tubular railing.
- Install architectural treatment along sides of parapets.
- Install curb plates along edges of sidewalk.
- Install roadway underdrain and drainage structures.
- Reinstall driveway aprons.
- Install roadway aggregates and asphalt.
- Lane striping and signage reinstalled.
- Topsoil, seeding, and mulching.
July 1, 2026
Progress:
- Cofferdam shoring installed at forward side for excavation support of waterline along left side of roadway.
- Temporary shoring wall along driveway at forward right side of proposed structure.
- Form, tie rebar, and pour concrete into rear abutment footer and knee wall.
- Form, tie rebar, and pour concrete into forward abutment footer and knee wall.
- Rock Excavation for proposed rear and forward abutment footer.
Upcoming Work:
- Erect precast arches, headwall, and wingwalls.
- Waterproofing, grouting, and installing drainage within bridge structure.
- Install rock channel protection along sides of creek bank.
- Install embankment to backfill footers.
- Install structural backfill and roadway aggregates.
June 8, 2026
Progress:
- Ridgewood drive closed May 4th to begin the demolition and full replacement of Ridgewood Bridge Culver 03.50 over West Creek.
- Guardrail removal.
- Demolished portions of roadway, superstructure, and substructure.
- Excavation for rear and forward abutments.
- Cofferdam shoring was installed at rear side for excavation support of waterline along left side of roadway.
Upcoming Work:
- Cofferdam shoring install at forward side for excavation support of waterline along left side of roadway.
- Form, tie rebar, and pour concrete into rear abutment footer.
- Form, tie rebar, and pour concrete into rear abutment knee wall.
- Form, tie, rebar, and pour concrete into forward abutment footer.
- Erect precast arches, headwall, and wingwalls.
May 4, 2026
Progress:
- Installation of resident temporary access drive.
- Telecom companies completed relocation of facilities.
- Equipment mobilized to site and laydown area established.
- Waterline along left side of bridge field verified.
Upcoming Work:
- Date for closure of Ridgewood Bridge is Monday, May 4th, 2026.
- This work will include a total replacement of the Ridgewood Bridge Culvert 03.50 over West Creek.
- The road will be closed to through traffic for a 90-day period.
- Guardrail removal.
- Demolish roadway, superstructure, and substructure.
- Excavation, tie rebar, and pour concrete into rear abutment.
April 3, 2026
Progress:
- Contractors onsite to complete tree removal along east side of the roadway that are necessary for access during construction.
- Removal was done prior to start of construction to maintain environmental commitments.
- Utilities onsite to complete relocation of facilities.
Upcoming Work:
- Tentative date for closure of Ridgewood Bridge is May 4th, 2026.
- This work will include a total replacement of the Ridgewood Bridge Culvert 03.50 over West Creek.
- The road will be closed to through traffic for a 90-day period.
- Installation of resident temporary access drive.
- Additional utility companies are onsite to complete the relocation of facilities.