Construction Updates

St. Clair Avenue Bridge 04.44 Over Doan Brook - City of Cleveland
CONTACTS
Contractor: Perk Company, Inc.

County: Ryan Maver 216-348-3819
Brian Vigh 216-301-9010
DATES
Start Date: 09-01-2024
Notice To Proceed Date: 09-01-2024
Completion Date:
Scheduled Completion Date: 11-30-2025
Anticipated Completion Date: 11-30-2025
AMOUNTS
Project Amount($):
Contract Award Amount($): 3,070,280.45
Estimated Cost To Completion($): $2,334,327.03
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
PROGRESS

February 4, 2025

Current Zone

  • No work one has been established; St. Clair is completely open to normal traffic pattern.

 

PROGRESS:

  • Contractor has been drilling the shafts for the new wingwall foundation.

St. Clair Avenue Bride Construction    St. Clair Avenue Bride Construction

 

January 2, 2025

Current Zone

  • No work one has been established; St. Clair is completely open to normal traffic pattern.

 

PROGRESS:

  • The contractor successfully completed the shoring wall to be able to progress into further construction of the new foundation for the wingwall of the bridge.

 

December 3, 2024

Current Zone

  • No work one has been established; St. Clair is completely open to normal traffic pattern.

Progress

  • Contractor has been working on completing the temporary shoring system to begin the shafts for the new foundation of the bridge wingwall.

St. Clair Avenue Bridge 04.44 Construction  Construction Site

Current Zone

  • No work one has been established; St. Clair is completely open to normal traffic pattern.

November 5, 2024

  • Perk Company is finishing the previously started project through Chagrin Valley Paving under bond.
  • Contractor began cleaning up the construction site and are currently working on repairing the bridge wingwall by first installing a temporary tie-back shoring system.

St. Clair Bridge Construction    St. Clair Bridge Construction

December 1, 2023

  • No work was performed due to material delays.

September 12, 2023

  • No work was performed due to material delays.

July 5, 2023

  • Contractor next step is to work on bridge wingwall and the Doan Brook channel walls.
  • Work is pending VECP submission by the contractor.
  • No work was performed in the month of June.

May 4, 2023

  • Work zone has not been established. St. Clair is completely open to normal traffic pattern.
  • Contractor next step is to work on bridge wingwall and the Doan Brook channel walls.
  • Work is pending VECP submission by the contractor.
  • No work was performed in the month of April.

April 18, 2023

  • Work zone has not been established. St. Clair is completely open to normal traffic pattern.
  • Contractor next step is to work on bridge wingwall and the Doan Brook channel walls.
  • Work is pending VECP submission by the contractor.
  • No work was performed in the month of March.

 



  
How could we make it better? Leaving an email can assist us in troubleshooting the issue.
  
Thank you for your feedback
Your feedback means a lot to us. We use it to improve the experience of all of our users.