Construction Updates

St. Claire Avenue Bridge 04.44 Over Doan Brook - City of Cleveland
CONTACTS
Contractor: Chagrin Valley Paving
(440) 543-2253
County: Ryan Maver 216-348-3819
Brian Vigh 216-301-9010
DATES
Start Date: 05-01-2021
Notice To Proceed Date: 05-01-2021
Completion Date:
Scheduled Completion Date: 05-01-2022
Anticipated Completion Date: 06-01-2022
AMOUNTS
Project Amount($):
Contract Award Amount($): $1,976,777.57
Estimated Cost To Completion($): 0
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
PROGRESS

December 1, 2023

  • No work was performed due to material delays.

September 12, 2023

  • No work was performed due to material delays.

July 5, 2023

  • Contractor next step is to work on bridge wingwall and the Doan Brook channel walls.
  • Work is pending VECP submission by the contractor.
  • No work was performed in the month of June.

May 4, 2023

  • Work zone has not been established. St. Clair is completely open to normal traffic pattern.
  • Contractor next step is to work on bridge wingwall and the Doan Brook channel walls.
  • Work is pending VECP submission by the contractor.
  • No work was performed in the month of April.

April 18, 2023

  • Work zone has not been established. St. Clair is completely open to normal traffic pattern.
  • Contractor next step is to work on bridge wingwall and the Doan Brook channel walls.
  • Work is pending VECP submission by the contractor.
  • No work was performed in the month of March.