Construction Updates

W. 150th Bridge 0.194 Rehabilitation Over Chatfield Ave.
CONTACTS
Contractor: Schirmer Construction Company

County: Michael Gilbert 216-496-1377
Jon Osterstock
DATES
Start Date: 08-01-2024
Notice To Proceed Date: 08-01-2024
Completion Date:
Scheduled Completion Date: 07-31-2025
Anticipated Completion Date: 07-31-2025
AMOUNTS
Project Amount($):
Contract Award Amount($): 1,609,858.50
Estimated Cost To Completion($): $1,609,858.50
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

February 4, 2025

  • West pier patching
  • Maintenance of traffic phase I set-up and temporary striping.
  • Barrier wall emplacement above pier 5 in work zone.
  • Armstrong Steel to erect temporary support and jacking structure.
  • Night road closure for bridge jacking January 14, 2025 (night work).
  • Demolition work on west pier cap.

Work Expected:

  • Continuing demolition work on west pier cap.
  • Reinforcing steel instalment for west pier cap.
  • Form work for concrete of west pier cap.
  • Concrete pour for west pier cap.
  • Removing formwork and treating of surfaces for east pier cap.

Progress photo taken 1/28/25

West 150th Bridge Construction

January 8, 2025

  • West pier patching
  • Message boards emplaced at the north and south ends of the bridge.
  • Trafftech erected and covered all detour signage.
  • Jacking and support structure foundation set up.
  • Concrete pour patching on east pier north and south faces.

Work Expected:

  • Maintenance of traffic Phase I set up and temporary striping.
  • Barrier wall emplacement above pier 5 in work zone.
  • Armstrong Steel to erect temporary support and jacking structure.
  • Night road closure for bridge jacking January 14, 2025 (NIGHT WORK).
w150 construction

December 10, 2024

Progress:

  • Contractor work area set up and staging
  • Saw cutting and chipping disintegrated sections of Pier 5.
  • Forming up removed disintegrated sections for patching remediation.

Current Work Zone:

  • Pier 5 saw cutting and chipping of disintegrated concrete.
  • Forming up removed disintegrated sections for patching remediation.
  • Replacing corroded reinforcing bars.

West 150 Bridge Construction



  
How could we make it better? Leaving an email can assist us in troubleshooting the issue.
  
Thank you for your feedback
Your feedback means a lot to us. We use it to improve the experience of all of our users.