Construction Updates

Warrensville Center Road Bridges
CONTACTS
Contractor: Schirmer Construction LLC

County: Ryan Maver 440-759-2472
Mark Rinderman 440-221-2791
DATES
Start Date: 07-01-2023
Notice To Proceed Date: 07-01-2023
Completion Date:
Scheduled Completion Date: 07-01-2025
Anticipated Completion Date: 07-01-2025
AMOUNTS
Project Amount($):
Contract Award Amount($): $8,281,397.65
Estimated Cost To Completion($): $8,281,397.65
Approved Contract Increases($): AMENDED AGREEMENT #01 IN PROGRESS
Approved Contract Decreases($): 0
PROGRESS

September 3, 2024

  • Temporary protective structure over RTA under new NB bridge removed.
  • Demo of all existing SB structures completed.
  • Placement of substructure for proposed SB bridge complete.
  • Soil embanked, shaped for proposed SW/NW slopes adjacent to new SB bridge.
  • Removal of existing pavement and walks near complete on Phase 2 side.
  • Placement of cellular concrete fill completed on 8/22.
  • Placement of plate grinders #01 through #07.
  • Upcoming

  • Forming, placement of new SB bridge deck.
  • Placement of new 6-foot walk adjacent to new bridge deck
  • Construction of new approach slabs.


Notes

  • East Bridge (northbound bridge) was opened to bi-directional traffic on June 7th.
  • Project is on schedule to complete bridge work Fall 2024.
  • Project is currently running within anticipated cost, no major cost overruns anticipated at this time.
  • Flagmen as needed based on work type, onsite to monitor project work adjacent to RTA tracks, ensure safety of rail traffic/project workforce.

Maintenance of Traffic

  • All Warrensville Road traffic is now using the new east bridge, one lane northbound, one lane southbound.
  • West bridge is closed, including walkway.
  • Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east and west.
  • Shaker Heights Police is on site as needed to monitor work zone, enforce safety.
  • Posted detour is in place to reroute traffic onto Shaker Blvd. east and west from Warrensville Road.
  • Pedestrians and bicyclists PROHIBITED from entering work zones north and south of the closed bridge. Follow posted signs at open crosswalks.
  • East sidewalk on new east bridge is open.
  • ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKTED BY THE SHAKER POLICE.
  • DANGEROUS CONDITIONS EXIST WITHIN CLOSED ZONE.

 

July 3, 2024

  • Phase I construction of northbound bridge complete.
  • Shaping of slopes, seeding/mulching of areas adjacent to new bridge complete.
  • Traffic now using the new northbound bridge per flip from Phase I to Phase II on June 7th.
  • Phase II southbound bridge closed, existing box beams from both spans removed.

     

    Upcoming

  • Demo work on rear/forward abutments of southbound bridge structure.
  • Demo work on wingwalls of southbound bridge structure.
  • Placement of concrete for new portions of abutments.
  • Removal of temporary falsework/protective structure under new northbound bridge.
  • RTA closing rail lines under project per one month shutdown beginning July 7th.
  • Contractor scheduled to have two crews on site to expedite work during this time.


Notes

  • East Bridge (northbound bridge) was opened to bi-directional traffic on June 7th.
  • Project is on schedule to complete bridge work Fall 2024.
  • Project is currently running within anticipated cost, no major cost  overruns anticipated at this time.
  • Flagmen on site to monitor project work adjacent to RTA tracks, ensure safety of rail traffic/project workforce.

Maintenance of Traffic

 

  • All Warrensville Road traffic is now using the new east bridge, one lane northbound, one lane southbound.
  • West bridge is closed, including walking.
  • Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east and west.
  • Shaker Heights Police is on site as needed to monitor work zone, enforce safety.
  • Posted detour is in place to reroute traffic onto Shaker Blvd. east and west from Warrensville Road.
  • Pedestrians and bicyclists PROHIBITED from entering work zones north and south of the closed bridge. Follow posted signs at open crosswalks.
  • East sidewalk on new east bridge is open.

     

  • ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKED BY THE SHAKER POLICE.

     

  • DANGEROUS CONDITIONS EXIST WITHIN CLOSED ZONE.

 

May 7, 2024

  • Bridge deck placed, out of cure, and deck grooving this week.
  • Approach slabs completed out of cure, grooving this week.
  • Parapet walls on bridge nearly completed, wall ends on decorative wall will be completed this week.
  • New concrete placement for Phase I has been completed on the north side of the bridge.
  • Pavement removal south of bridge, Phase I is complete. 

March 20, 2024

  • New drive for Shaker Fire Department complete, now open to emergency vehicles.
  • Placement of new 9” concrete base in front of fire drive, 38+50 TO 38+95 right, now complete.
  • The sidewalk install north of the fire drive is complete.
  • Phase I girder/bearing placement now complete for new NB bridge structure.

Upcoming

  • Shaping, grading new slope profile at southeast/northeast wingwalls.
  • Construction, forming of superstructure (deck) for new NB bridge.
  • Concrete placement for new deck on NB Bridge.
  • Remove existing pavement, commercial drive south of NB Bridge from 34+88 to 36+75 right.
  • Construction of approach slabs for NB Bridge.
  • Placement of soils as embankment per new bridge elevations in area of Shaker Fire Department.
  • Topsoil, seeding of areas adjacent to new fire drive, new walk north of fire drive.

Notes

  • Anticipated completion for east structure is late spring, early summer of 2024.
  • After traffic switches to east bridge, west bridge will be closed/demolished.
  • Major items of work are to be completed in late 2024.
  • DO NOT ENTER CLOSED WORK ZONE AT EAST BRIDGE, DANGEROUS CONDITIONS EXIST

Maintenance of Traffic

  • All traffic now uses west bridge, one lane northbound, one lane southbound.
  • East bridge is closed, INCLUDING SIDWALK.
  • Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east/west.
  • Posted detour is in place to reroute traffic having to get to Shaker Blvd. from Warrensville Road within the work zone.
  • Pedestrians and bicyclists are PROHIBITED from entering work zones north and south of closed bridge. Follow posted signs at open crosswalks.
  • West sidewalk on west bridge is open.
  • ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKETED BY THE SHAKER POLICE.
  • DANGEROUS CONDITIONS EXIST WITHIN CLOSED ZONE.

February 23, 2024

  • Basins, manhole, and conduits installed as new drainage system for fire station drive.
  • Remove south half of the fire drive, existing concrete roadway.
  • Placed a new 9” concrete base in front of the fire drive.
  • Completed additional work to correct drainage failures found in existing conduits at the fire station drive.

Upcoming

  • Shaping, grading new slope profile at southeast/northeast wingwalls.
  • Remove the remainder of existing pavement from fire drive to north limit.
  • Construction, placement of new 8” reinforced pavement for drive at Shaker Fire Department.
  • Construction on new 9” concrete base pavement.
  • Fabrication, painting of bridge girders for east/west bridge structures.
  • Placement of bearing ends, erection of girders G8 through G16.
  • Construction, forming of superstructure for new east bridge.

Notes

  • Delivery of girders for the Phase I side, tentatively scheduled for March 11, 2024.
  • Anticipated completion for east structure is late spring, early summer of 2024.
  • After traffic switches to east bridge, west bridge will be closed/demolished.
  • Major items of work are to be completed late 2024.
  • DO NOT ENTER CLOSED WORK ZONE AT EAST BRIDGE, DANGEROUS CONDITIONS EXIST

Maintenance of Traffic

  • All traffic now uses west bridge, one lane northbound, one lane southbound.
  • East bridge is closed, INCLUDING SIDWALK.
  • Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east/west.
  • Posted detour is in place to reroute traffic having to get to Shaker Blvd. from Warrensville Road within the work zone.
  • Pedestrians and bicyclists are PROHIBITED from entering work zones north and south of closed bridge. Follow posted signs at open crosswalks.
  • West sidewalk on west bridge is open.
  • ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKETED BY THE SHAKER POLICE.
  • DANGEROUS CONDITIONS EXIST WITHIN CLOSED ZONE.

January 3, 2024

  • Phase I construction of all new east bridge structures are completed the rear/forward sides, with exception of parapet walls. · Phase I waterproofing of abutments, center retaining walls, wing walls complete. · Phase I abutment excavation, placement of cellular concrete fill complete. · Fabrication of curb plates for both bridge structures is complete.

Upcoming

  • Shaping, grading new slope profile off southeast wingwall.
  • Placement of conduits, basins and manhole for proposed drainage work at fire station.
  • Removal of existing pavement, construction of new pavement for fire station drive apron.
  • Fabrication of bridge girders for both bridge structures.

Notes

  • Project schedule has been changed to move up completion date. This will result in work being performed through winter.
  • Anticipated completion for east structure is late spring, early summer of 2024.
  • Once traffic is switched over to east bridge, west bridge will be closed and demolished.
  • Major items of work are anticipated to be completed, with both bridges open to traffic by late 2024.
  • The progress of work on site during winter months is weather dependent.
  • Project is currently on schedule to have both bridge structures complete by end of 2024.
  • Fabrication of steel girders for new bridge structures is currently underway, delivery in late February.
  • DO NOT ENTER CLOSED WORK ZONE AT EAST BRIDGE, DANGEROUS CONDITIONS EXIST

Maintenance of Traffic

  • All traffic now uses west bridge, one lane northbound, one lane southbound.
  • East bridge is closed, INCLUDING SIDWALK.
  • Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east/west.
  • Posted detour is in place to reroute traffic having to get to Shaker Blvd. from Warrensville Road within the work zone.
  • Pedestrians and bicyclists are PROHIBITED from entering work zones north and south of closed bridge. Follow posted signs at open crosswalks.
  • West sidewalk on west bridge is open.
  • ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKETED BY THE SHAKER POLICE.

November 21, 2023

  • Phase I demolition of existing east bridge structure is complete.
  • Phase I construction of new east bridge structures complete on rear side, with exception of parapet wall.
  • Removal of approach slabs on Phase I side complete.

Upcoming

  • Reconstruction of forward center retaining wall, forward abutment, NE wing wall, and pier cap.
  • Excavating behind abutments, retaining walls, including waterproofing of same.
  • Placement of low density cellular concrete fill behind abutments, retaining walls.
  • Shaping, grading new slope profile off southeast wingwall.

October 10, 2023

  • Existing box beams, both spans of east bridge removed.
  • Demolition of rear/forward abutments, center retaining wall portions complete.
  • Rear abutment re-construction, including concrete placement complete.
Upcoming
  • Reconstruction of center retaining walls, SE/NE wing walls, including concrete placement.
  • Reconstruction of forward abutment portions.
  • Demo of existing pier cap, east bridge structure.
  • Excavation, waterproofing, and backfill of abutments with engineered fill.
Notes
  • Project is schedule has been changed to move up completion date. This will result in work being performed through winter.
  • Anticipated completion for east structure is late spring, early summer of 2024.
  • Once traffic is switched over to east bridge, west bridge will be closed and demolished.
  • Major items of work are anticipated to be completed, with both bridges open to traffic by late 2024.
  • RTA outage now over, bridge work ongoing with RTA fully operational.
  • Project is on schedule, based on work completed for east bridge structure.
Maintenance of Traffic
  • All traffic now uses west bridge, one lane northbound, one lane southbound.
  • East bridge is closed, INCLUDING SIDWALK.
  • Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east/west.
  • Posted detour is in place to reroute traffic having to get to Shaker Blvd. from Warrensville Road within the work zone.
  • Pedestrians and bicyclists are PROHIBITED from entering work zones north and south of closed bridges. Follow posted signs at open crosswalks.
  • West sidewalk on westbound bridge is open.
  • ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKETED BY THE SHAKER POLICE.

 

August 28, 2023

Phase I

  • Asphalt and crossovers have been completed.
  • Traffic has been switched to one lane in each direction onto westbound bridge structure on 8/8 eastbound bridge is closed.
  • Guardrails, vandal fence removed from eastbound bridge in preparation for demolition.
  • Removal of sidewalks, curbs, traffic islands and pavement are in progress.
  • Construction of temporary shoring structure under bridges over RTA tracks started on 8/21.
Upcoming
  • Completion of temporary shoring structure under both bridges.
  • Excavation behind abutments prior to bridge demolition.
  • Demolition of existing eastbound bridge.
Notes
  • Project schedule has been changed to move the completion date. This will result in work being performed thought the winter.
  • Anticipated completion for eastbound structure is late spring, early summer of 2024.
  • Once traffic is switched over to the eastbound bridge, the westbound bridge will be closed and demolished.
  • Major items of work are anticipated to be completed, with both bridges open to traffic by late 2024.
Maintenance of Traffic
  • All traffic now uses westbound bridge, one lane northbound, one lane southbound.
  • Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east/west.
  • Posted detour is in place to reroute traffic having to get to Shaker Blvd. from Warrensville Road within the work zone.
  • Pedestrians and bicyclists are PROHIBITED from entering work zones north and south of closed bridges. Follow posted signs at open crosswalks.
  • West sidewalk on westbound bridge is open.
  • ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKETED BY THE SHAKER POLICE.

 

July 28, 2023

Phase I

  • Building temporary crossovers to reroute all Warrensville Center Road traffic to the southbound bridge.
  • August 8th  Phase I closing the northbound bridge to all traffic. Two-way traffic will be maintained on the southbound bridge.
  • Phase I will be in place until late spring 2024.
  • Please be advised left turns will be prohibited for southbound Warrensville traffic at Shaker Blvd., eastbound, and for northbound Warrensville traffic at Shaker Blvd., westbound.


  