Construction Updates
◄
Warrensville Center Road Bridges PROJECT DETAIL
CONTACTS
DATES
Start Date: 07-01-2023
Notice To Proceed Date: 07-01-2023
Completion Date:
Notice To Proceed Date: 07-01-2023
Completion Date:
Scheduled Completion Date: 07-01-2025
Anticipated Completion Date: 07-01-2025
Anticipated Completion Date: 07-01-2025
AMOUNTS
Project Amount($):
Contract Award Amount($): $8,281,397.65
Estimated Cost To Completion($): $8,281,397.65
Contract Award Amount($): $8,281,397.65
Estimated Cost To Completion($): $8,281,397.65
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
Approved Contract Decreases($): 0
PROGRESS
May 7, 2024
- Bridge deck placed, out of cure, and deck grooving this week.
- Approach slabs completed out of cure, grooving this week.
- Parapet walls on bridge nearly completed, wall ends on decorative wall will be completed this week.
- New concrete placement for Phase I has been completed on the north side of the bridge.
- Pavement removal south of bridge, Phase I is complete.
March 20, 2024
- New drive for Shaker Fire Department complete, now open to emergency vehicles.
- Placement of new 9” concrete base in front of fire drive, 38+50 TO 38+95 right, now complete.
- The sidewalk install north of the fire drive is complete.
- Phase I girder/bearing placement now complete for new NB bridge structure.
Upcoming
- Shaping, grading new slope profile at southeast/northeast wingwalls.
- Construction, forming of superstructure (deck) for new NB bridge.
- Concrete placement for new deck on NB Bridge.
- Remove existing pavement, commercial drive south of NB Bridge from 34+88 to 36+75 right.
- Construction of approach slabs for NB Bridge.
- Placement of soils as embankment per new bridge elevations in area of Shaker Fire Department.
- Topsoil, seeding of areas adjacent to new fire drive, new walk north of fire drive.
Notes
- Anticipated completion for east structure is late spring, early summer of 2024.
- After traffic switches to east bridge, west bridge will be closed/demolished.
- Major items of work are to be completed in late 2024.
- DO NOT ENTER CLOSED WORK ZONE AT EAST BRIDGE, DANGEROUS CONDITIONS EXIST
Maintenance of Traffic
- All traffic now uses west bridge, one lane northbound, one lane southbound.
- East bridge is closed, INCLUDING SIDWALK.
- Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east/west.
- Posted detour is in place to reroute traffic having to get to Shaker Blvd. from Warrensville Road within the work zone.
- Pedestrians and bicyclists are PROHIBITED from entering work zones north and south of closed bridge. Follow posted signs at open crosswalks.
- West sidewalk on west bridge is open.
- ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKETED BY THE SHAKER POLICE.
- DANGEROUS CONDITIONS EXIST WITHIN CLOSED ZONE.
February 23, 2024
- Basins, manhole, and conduits installed as new drainage system for fire station drive.
- Remove south half of the fire drive, existing concrete roadway.
- Placed a new 9” concrete base in front of the fire drive.
- Completed additional work to correct drainage failures found in existing conduits at the fire station drive.
Upcoming
- Shaping, grading new slope profile at southeast/northeast wingwalls.
- Remove the remainder of existing pavement from fire drive to north limit.
- Construction, placement of new 8” reinforced pavement for drive at Shaker Fire Department.
- Construction on new 9” concrete base pavement.
- Fabrication, painting of bridge girders for east/west bridge structures.
- Placement of bearing ends, erection of girders G8 through G16.
- Construction, forming of superstructure for new east bridge.
Notes
- Delivery of girders for the Phase I side, tentatively scheduled for March 11, 2024.
- Anticipated completion for east structure is late spring, early summer of 2024.
- After traffic switches to east bridge, west bridge will be closed/demolished.
- Major items of work are to be completed late 2024.
- DO NOT ENTER CLOSED WORK ZONE AT EAST BRIDGE, DANGEROUS CONDITIONS EXIST
Maintenance of Traffic
- All traffic now uses west bridge, one lane northbound, one lane southbound.
- East bridge is closed, INCLUDING SIDWALK.
- Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east/west.
- Posted detour is in place to reroute traffic having to get to Shaker Blvd. from Warrensville Road within the work zone.
- Pedestrians and bicyclists are PROHIBITED from entering work zones north and south of closed bridge. Follow posted signs at open crosswalks.
- West sidewalk on west bridge is open.
- ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKETED BY THE SHAKER POLICE.
- DANGEROUS CONDITIONS EXIST WITHIN CLOSED ZONE.
January 3, 2024
- Phase I construction of all new east bridge structures are completed the rear/forward sides, with exception of parapet walls. · Phase I waterproofing of abutments, center retaining walls, wing walls complete. · Phase I abutment excavation, placement of cellular concrete fill complete. · Fabrication of curb plates for both bridge structures is complete.
Upcoming
- Shaping, grading new slope profile off southeast wingwall.
- Placement of conduits, basins and manhole for proposed drainage work at fire station.
- Removal of existing pavement, construction of new pavement for fire station drive apron.
- Fabrication of bridge girders for both bridge structures.
Notes
- Project schedule has been changed to move up completion date. This will result in work being performed through winter.
- Anticipated completion for east structure is late spring, early summer of 2024.
- Once traffic is switched over to east bridge, west bridge will be closed and demolished.
- Major items of work are anticipated to be completed, with both bridges open to traffic by late 2024.
- The progress of work on site during winter months is weather dependent.
- Project is currently on schedule to have both bridge structures complete by end of 2024.
- Fabrication of steel girders for new bridge structures is currently underway, delivery in late February.
- DO NOT ENTER CLOSED WORK ZONE AT EAST BRIDGE, DANGEROUS CONDITIONS EXIST
Maintenance of Traffic
- All traffic now uses west bridge, one lane northbound, one lane southbound.
- East bridge is closed, INCLUDING SIDWALK.
- Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east/west.
- Posted detour is in place to reroute traffic having to get to Shaker Blvd. from Warrensville Road within the work zone.
- Pedestrians and bicyclists are PROHIBITED from entering work zones north and south of closed bridge. Follow posted signs at open crosswalks.
- West sidewalk on west bridge is open.
- ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKETED BY THE SHAKER POLICE.
November 21, 2023
- Phase I demolition of existing east bridge structure is complete.
- Phase I construction of new east bridge structures complete on rear side, with exception of parapet wall.
- Removal of approach slabs on Phase I side complete.
Upcoming
- Reconstruction of forward center retaining wall, forward abutment, NE wing wall, and pier cap.
- Excavating behind abutments, retaining walls, including waterproofing of same.
- Placement of low density cellular concrete fill behind abutments, retaining walls.
- Shaping, grading new slope profile off southeast wingwall.
October 10, 2023
- Existing box beams, both spans of east bridge removed.
- Demolition of rear/forward abutments, center retaining wall portions complete.
- Rear abutment re-construction, including concrete placement complete.
- Reconstruction of center retaining walls, SE/NE wing walls, including concrete placement.
- Reconstruction of forward abutment portions.
- Demo of existing pier cap, east bridge structure.
- Excavation, waterproofing, and backfill of abutments with engineered fill.
- Project is schedule has been changed to move up completion date. This will result in work being performed through winter.
- Anticipated completion for east structure is late spring, early summer of 2024.
- Once traffic is switched over to east bridge, west bridge will be closed and demolished.
- Major items of work are anticipated to be completed, with both bridges open to traffic by late 2024.
- RTA outage now over, bridge work ongoing with RTA fully operational.
- Project is on schedule, based on work completed for east bridge structure.
- All traffic now uses west bridge, one lane northbound, one lane southbound.
- East bridge is closed, INCLUDING SIDWALK.
- Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east/west.
- Posted detour is in place to reroute traffic having to get to Shaker Blvd. from Warrensville Road within the work zone.
- Pedestrians and bicyclists are PROHIBITED from entering work zones north and south of closed bridges. Follow posted signs at open crosswalks.
- West sidewalk on westbound bridge is open.
- ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKETED BY THE SHAKER POLICE.
August 28, 2023
Phase I
- Asphalt and crossovers have been completed.
- Traffic has been switched to one lane in each direction onto westbound bridge structure on 8/8 eastbound bridge is closed.
- Guardrails, vandal fence removed from eastbound bridge in preparation for demolition.
- Removal of sidewalks, curbs, traffic islands and pavement are in progress.
- Construction of temporary shoring structure under bridges over RTA tracks started on 8/21.
- Completion of temporary shoring structure under both bridges.
- Excavation behind abutments prior to bridge demolition.
- Demolition of existing eastbound bridge.
- Project schedule has been changed to move the completion date. This will result in work being performed thought the winter.
- Anticipated completion for eastbound structure is late spring, early summer of 2024.
- Once traffic is switched over to the eastbound bridge, the westbound bridge will be closed and demolished.
- Major items of work are anticipated to be completed, with both bridges open to traffic by late 2024.
- All traffic now uses westbound bridge, one lane northbound, one lane southbound.
- Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east/west.
- Posted detour is in place to reroute traffic having to get to Shaker Blvd. from Warrensville Road within the work zone.
- Pedestrians and bicyclists are PROHIBITED from entering work zones north and south of closed bridges. Follow posted signs at open crosswalks.
- West sidewalk on westbound bridge is open.
- ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKETED BY THE SHAKER POLICE.
July 28, 2023
Phase I
- Building temporary crossovers to reroute all Warrensville Center Road traffic to the southbound bridge.
- August 8th Phase I closing the northbound bridge to all traffic. Two-way traffic will be maintained on the southbound bridge.
- Phase I will be in place until late spring 2024.
- Please be advised left turns will be prohibited for southbound Warrensville traffic at Shaker Blvd., eastbound, and for northbound Warrensville traffic at Shaker Blvd., westbound.