Department of Public Works

The Cuyahoga County Department of Public Works provides a safe and efficient infrastructure system for residents, employees, businesses, and visitors of Cuyahoga County. The key function of the Public Works Department is to build and maintain public infrastructure and facilities.

Popular Services

bridge iconVeterans Memorial Bridge

Rediscover this landmark through the initiative to reopen its historic streetcar level.

 

 Design/Construction

Access documents & information related to bridge, highway, sanitary, & other construction.

 

 Courthouse Rentals

Facility rentals at the Old Courthouse. Book your wedding or special event!

 

 Sewer Maintenance

Public Works provides maintenance services for sewers throughout the County.

 

Construction Updates

St. Claire Avenue Bridge 04.44 Over Doan Brook - City of Cleveland
CONTACTS
Contractor: Chagrin Valley Paving
(440) 543-2253
County: Ryan Maver 216-348-3819
Brian Vigh 216-301-9010
DATES
Start Date: 05-01-2021
Notice To Proceed Date: 05-01-2021
Completion Date:
Scheduled Completion Date: 05-01-2022
Anticipated Completion Date: 06-01-2022
AMOUNTS
Project Amount($):
Contract Award Amount($): $1,976,777.57
Estimated Cost To Completion($): 0
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
PROGRESS

December 1, 2023

  • No work was performed due to material delays.

September 12, 2023

  • No work was performed due to material delays.

July 5, 2023

  • Contractor next step is to work on bridge wingwall and the Doan Brook channel walls.
  • Work is pending VECP submission by the contractor.
  • No work was performed in the month of June.

May 4, 2023

  • Work zone has not been established. St. Clair is completely open to normal traffic pattern.
  • Contractor next step is to work on bridge wingwall and the Doan Brook channel walls.
  • Work is pending VECP submission by the contractor.
  • No work was performed in the month of April.

April 18, 2023

  • Work zone has not been established. St. Clair is completely open to normal traffic pattern.
  • Contractor next step is to work on bridge wingwall and the Doan Brook channel walls.
  • Work is pending VECP submission by the contractor.
  • No work was performed in the month of March.