Department of Public Works

The Cuyahoga County Department of Public Works provides a safe and efficient infrastructure system for residents, employees, businesses, and visitors of Cuyahoga County. The key function of the Public Works Department is to build and maintain public infrastructure and facilities.

Popular Services

bridge iconVeterans Memorial Bridge

Rediscover this landmark through the initiative to reopen its historic streetcar level.

 

 Design/Construction

Access documents & information related to bridge, highway, sanitary, & other construction.

 

 Courthouse Rentals

Facility rentals at the Old Courthouse. Book your wedding or special event!

 

 Sewer Maintenance

Public Works provides maintenance services for sewers throughout the County.

 

Construction Updates

W. 150th Bridge 0.194 Rehabilitation Over Chatfield Ave.
CONTACTS
Contractor: Schirmer Construction Company

County: Michael Gilbert 216-496-1377
Jon Osterstock
DATES
Start Date: 08-01-2024
Notice To Proceed Date: 08-01-2024
Completion Date:
Scheduled Completion Date: 07-31-2025
Anticipated Completion Date: 07-31-2025
AMOUNTS
Project Amount($):
Contract Award Amount($): 1,609,858.50
Estimated Cost To Completion($): $1,609,858.50
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

January 8, 2025

  • West pier patching
  • Message boards emplaced at the north and south ends of the bridge.
  • Trafftech erected and covered all detour signage.
  • Jacking and support structure foundation set up.
  • Concrete pour patching on east pier north and south faces.

Work Expected:

  • Maintenance of traffic Phase I set up and temporary striping.
  • Barrier wall emplacement above pier 5 in work zone.
  • Armstrong Steel to erect temporary support and jacking structure.
  • Night road closure for bridge jacking January 14, 2025 (NIGHT WORK).
w150 construction

December 10, 2024

Progress:

  • Contractor work area set up and staging
  • Saw cutting and chipping disintegrated sections of Pier 5.
  • Forming up removed disintegrated sections for patching remediation.

Current Work Zone:

  • Pier 5 saw cutting and chipping of disintegrated concrete.
  • Forming up removed disintegrated sections for patching remediation.
  • Replacing corroded reinforcing bars.