Department of Public Works

The Cuyahoga County Department of Public Works provides a safe and efficient infrastructure system for residents, employees, businesses, and visitors of Cuyahoga County. The key function of the Public Works Department is to build and maintain public infrastructure and facilities.

Popular Services

bridge iconVeterans Memorial Bridge

Rediscover this landmark through the initiative to reopen its historic streetcar level.

 

 Design/Construction

Access documents & information related to bridge, highway, sanitary, & other construction.

 

 Courthouse Rentals

Facility rentals at the Old Courthouse. Book your wedding or special event!

 

 Sewer Maintenance

Public Works provides maintenance services for sewers throughout the County.

 

Construction Updates

Warrensville Center Road Bridges
CONTACTS
Contractor: Schirmer Construction LLC

County: Ryan Maver 440-759-2472
Mark Rinderman 440-221-2791
DATES
Start Date: 07-01-2023
Notice To Proceed Date: 07-01-2023
Completion Date:
Scheduled Completion Date: 07-01-2025
Anticipated Completion Date: 07-01-2025
AMOUNTS
Project Amount($):
Contract Award Amount($): $8,281,397.65
Estimated Cost To Completion($): $8,281,397.65
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
PROGRESS

March 20, 2024

  • New drive for Shaker Fire Department complete, now open to emergency vehicles.
  • Placement of new 9” concrete base in front of fire drive, 38+50 TO 38+95 right, now complete.
  • The sidewalk install north of the fire drive is complete.
  • Phase I girder/bearing placement now complete for new NB bridge structure.

Upcoming

  • Shaping, grading new slope profile at southeast/northeast wingwalls.
  • Construction, forming of superstructure (deck) for new NB bridge.
  • Concrete placement for new deck on NB Bridge.
  • Remove existing pavement, commercial drive south of NB Bridge from 34+88 to 36+75 right.
  • Construction of approach slabs for NB Bridge.
  • Placement of soils as embankment per new bridge elevations in area of Shaker Fire Department.
  • Topsoil, seeding of areas adjacent to new fire drive, new walk north of fire drive.

Notes

  • Anticipated completion for east structure is late spring, early summer of 2024.
  • After traffic switches to east bridge, west bridge will be closed/demolished.
  • Major items of work are to be completed in late 2024.
  • DO NOT ENTER CLOSED WORK ZONE AT EAST BRIDGE, DANGEROUS CONDITIONS EXIST

Maintenance of Traffic

  • All traffic now uses west bridge, one lane northbound, one lane southbound.
  • East bridge is closed, INCLUDING SIDWALK.
  • Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east/west.
  • Posted detour is in place to reroute traffic having to get to Shaker Blvd. from Warrensville Road within the work zone.
  • Pedestrians and bicyclists are PROHIBITED from entering work zones north and south of closed bridge. Follow posted signs at open crosswalks.
  • West sidewalk on west bridge is open.
  • ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKETED BY THE SHAKER POLICE.
  • DANGEROUS CONDITIONS EXIST WITHIN CLOSED ZONE.

February 23, 2024

  • Basins, manhole, and conduits installed as new drainage system for fire station drive.
  • Remove south half of the fire drive, existing concrete roadway.
  • Placed a new 9” concrete base in front of the fire drive.
  • Completed additional work to correct drainage failures found in existing conduits at the fire station drive.

Upcoming

  • Shaping, grading new slope profile at southeast/northeast wingwalls.
  • Remove the remainder of existing pavement from fire drive to north limit.
  • Construction, placement of new 8” reinforced pavement for drive at Shaker Fire Department.
  • Construction on new 9” concrete base pavement.
  • Fabrication, painting of bridge girders for east/west bridge structures.
  • Placement of bearing ends, erection of girders G8 through G16.
  • Construction, forming of superstructure for new east bridge.

Notes

  • Delivery of girders for the Phase I side, tentatively scheduled for March 11, 2024.
  • Anticipated completion for east structure is late spring, early summer of 2024.
  • After traffic switches to east bridge, west bridge will be closed/demolished.
  • Major items of work are to be completed late 2024.
  • DO NOT ENTER CLOSED WORK ZONE AT EAST BRIDGE, DANGEROUS CONDITIONS EXIST

Maintenance of Traffic

  • All traffic now uses west bridge, one lane northbound, one lane southbound.
  • East bridge is closed, INCLUDING SIDWALK.
  • Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east/west.
  • Posted detour is in place to reroute traffic having to get to Shaker Blvd. from Warrensville Road within the work zone.
  • Pedestrians and bicyclists are PROHIBITED from entering work zones north and south of closed bridge. Follow posted signs at open crosswalks.
  • West sidewalk on west bridge is open.
  • ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKETED BY THE SHAKER POLICE.
  • DANGEROUS CONDITIONS EXIST WITHIN CLOSED ZONE.

January 3, 2024

  • Phase I construction of all new east bridge structures are completed the rear/forward sides, with exception of parapet walls. · Phase I waterproofing of abutments, center retaining walls, wing walls complete. · Phase I abutment excavation, placement of cellular concrete fill complete. · Fabrication of curb plates for both bridge structures is complete.

Upcoming

  • Shaping, grading new slope profile off southeast wingwall.
  • Placement of conduits, basins and manhole for proposed drainage work at fire station.
  • Removal of existing pavement, construction of new pavement for fire station drive apron.
  • Fabrication of bridge girders for both bridge structures.

Notes

  • Project schedule has been changed to move up completion date. This will result in work being performed through winter.
  • Anticipated completion for east structure is late spring, early summer of 2024.
  • Once traffic is switched over to east bridge, west bridge will be closed and demolished.
  • Major items of work are anticipated to be completed, with both bridges open to traffic by late 2024.
  • The progress of work on site during winter months is weather dependent.
  • Project is currently on schedule to have both bridge structures complete by end of 2024.
  • Fabrication of steel girders for new bridge structures is currently underway, delivery in late February.
  • DO NOT ENTER CLOSED WORK ZONE AT EAST BRIDGE, DANGEROUS CONDITIONS EXIST

Maintenance of Traffic

  • All traffic now uses west bridge, one lane northbound, one lane southbound.
  • East bridge is closed, INCLUDING SIDWALK.
  • Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east/west.
  • Posted detour is in place to reroute traffic having to get to Shaker Blvd. from Warrensville Road within the work zone.
  • Pedestrians and bicyclists are PROHIBITED from entering work zones north and south of closed bridge. Follow posted signs at open crosswalks.
  • West sidewalk on west bridge is open.
  • ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKETED BY THE SHAKER POLICE.

November 21, 2023

  • Phase I demolition of existing east bridge structure is complete.
  • Phase I construction of new east bridge structures complete on rear side, with exception of parapet wall.
  • Removal of approach slabs on Phase I side complete.

Upcoming

  • Reconstruction of forward center retaining wall, forward abutment, NE wing wall, and pier cap.
  • Excavating behind abutments, retaining walls, including waterproofing of same.
  • Placement of low density cellular concrete fill behind abutments, retaining walls.
  • Shaping, grading new slope profile off southeast wingwall.

October 10, 2023

  • Existing box beams, both spans of east bridge removed.
  • Demolition of rear/forward abutments, center retaining wall portions complete.
  • Rear abutment re-construction, including concrete placement complete.
Upcoming
  • Reconstruction of center retaining walls, SE/NE wing walls, including concrete placement.
  • Reconstruction of forward abutment portions.
  • Demo of existing pier cap, east bridge structure.
  • Excavation, waterproofing, and backfill of abutments with engineered fill.
Notes
  • Project is schedule has been changed to move up completion date. This will result in work being performed through winter.
  • Anticipated completion for east structure is late spring, early summer of 2024.
  • Once traffic is switched over to east bridge, west bridge will be closed and demolished.
  • Major items of work are anticipated to be completed, with both bridges open to traffic by late 2024.
  • RTA outage now over, bridge work ongoing with RTA fully operational.
  • Project is on schedule, based on work completed for east bridge structure.
Maintenance of Traffic
  • All traffic now uses west bridge, one lane northbound, one lane southbound.
  • East bridge is closed, INCLUDING SIDWALK.
  • Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east/west.
  • Posted detour is in place to reroute traffic having to get to Shaker Blvd. from Warrensville Road within the work zone.
  • Pedestrians and bicyclists are PROHIBITED from entering work zones north and south of closed bridges. Follow posted signs at open crosswalks.
  • West sidewalk on westbound bridge is open.
  • ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKETED BY THE SHAKER POLICE.

 

August 28, 2023

Phase I

  • Asphalt and crossovers have been completed.
  • Traffic has been switched to one lane in each direction onto westbound bridge structure on 8/8 eastbound bridge is closed.
  • Guardrails, vandal fence removed from eastbound bridge in preparation for demolition.
  • Removal of sidewalks, curbs, traffic islands and pavement are in progress.
  • Construction of temporary shoring structure under bridges over RTA tracks started on 8/21.
Upcoming
  • Completion of temporary shoring structure under both bridges.
  • Excavation behind abutments prior to bridge demolition.
  • Demolition of existing eastbound bridge.
Notes
  • Project schedule has been changed to move the completion date. This will result in work being performed thought the winter.
  • Anticipated completion for eastbound structure is late spring, early summer of 2024.
  • Once traffic is switched over to the eastbound bridge, the westbound bridge will be closed and demolished.
  • Major items of work are anticipated to be completed, with both bridges open to traffic by late 2024.
Maintenance of Traffic
  • All traffic now uses westbound bridge, one lane northbound, one lane southbound.
  • Traffic on Warrensville Road within the work zone is PROHIBITED from making left turns onto Shaker Blvd. east/west.
  • Posted detour is in place to reroute traffic having to get to Shaker Blvd. from Warrensville Road within the work zone.
  • Pedestrians and bicyclists are PROHIBITED from entering work zones north and south of closed bridges. Follow posted signs at open crosswalks.
  • West sidewalk on westbound bridge is open.
  • ABSOLUTELY NO TRESSPASSERS ONTO CLOSED BRIDGE SITE. TRESPASSERS WILL BE TICKETED BY THE SHAKER POLICE.

 

July 28, 2023

Phase I

  • Building temporary crossovers to reroute all Warrensville Center Road traffic to the southbound bridge.
  • August 8th  Phase I closing the northbound bridge to all traffic. Two-way traffic will be maintained on the southbound bridge.
  • Phase I will be in place until late spring 2024.
  • Please be advised left turns will be prohibited for southbound Warrensville traffic at Shaker Blvd., eastbound, and for northbound Warrensville traffic at Shaker Blvd., westbound.