Department of Public Works

The Cuyahoga County Department of Public Works provides a safe and efficient infrastructure system for residents, employees, businesses, and visitors of Cuyahoga County. The key function of the Public Works Department is to build and maintain public infrastructure and facilities.

Popular Services

bridge iconVeterans Memorial Bridge

Rediscover this landmark through the initiative to reopen its historic streetcar level.

 

 Design/Construction

Access documents & information related to bridge, highway, sanitary, & other construction.

 

 Courthouse Rentals

Facility rentals at the Old Courthouse. Book your wedding or special event!

 

 Sewer Maintenance

Public Works provides maintenance services for sewers throughout the County.

 

Construction Updates

◄

West 140th Street Resurface Existing Roadway - City of Cleveland
CONTACTS
Contractor: Perk Company, Inc.

County: Craig Nauman
Robert Willis 216-308-2080
DATES
Start Date: 07-01-2026
Notice To Proceed Date: 07-01-2026
Completion Date:
Scheduled Completion Date: 10-31-2026
Anticipated Completion Date: 10-31-2026
AMOUNTS
Project Amount($):
Contract Award Amount($): 4,742,557.06
Estimated Cost To Completion($): $4,742,557.06
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

October 2, 2026

Progress:

  • Phase II Lorain Avenue to Triskett Avenue asphalt milling
  • Intermediate paving
  • Surface paving
  • ADA paving
  • Casting adjustments
  • Phase I final striping
  • Landscaping Phase II

Upcoming Work:

  • Final striping Phase II
  • Work completed for 2026 season
  • Work estimates to begin on Phase III in March 2027.

 

September 3, 2026

Progress:

  • Surface paving.
  • Temporary striping.
  • Landscaping for Phase I.

Upcoming Work:

  • Phase II to begin 9/8/26.
  • Asphalt milling Phase II.
  • Intermediate paving Phase II.

 

August 4, 2026

Progress:

  • Asphalt milling.
  • Intermediate paving.
  • ADA and sidewalk.
  • Casting adjustments.

Upcoming Work:

  • Landscaping for east side phase.
  • Flip traffic.
  • Asphalt milling (west side).
  • Intermediate paving (west side).