Old Rockside Bridge - Independence & Valley View
CONTACTS
Contractor: Kenmore Construction Company
(330) 762-9373
County: Darwin Merdes
Joshua Banaszak
DATES
Start Date: 06-01-2022
Notice To Proceed Date: 06-01-2022
Completion Date:
Scheduled Completion Date: 08-01-2022
Anticipated Completion Date: 08-01-2024
AMOUNTS
Project Amount($):
Contract Award Amount($): $7,348,986.42
Estimated Cost To Completion($): $7,348,986.42
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
PROGRESS

January 3, 2024

  • Traffic has been switched to the permanent bridge.
  • The temporary bridge has been removed, disassembled, and hauled off site.
  • Miscellaneous restoration tasks taking place around the project site including the Thornburg Station parking lot, and West Canal/Old Rockside intersection curb, paving business driveways on the west side of the bridge, etc.
  • Surface course asphalt and striping completed.

October 9, 2023

  • Traffic has been switched to the permanent bridge.
  • The temporary bridge is scheduled to be taken down in the upcoming weeks.
  • Miscellaneous restoration tasks taking place around project site.

September 28, 2023

  • Weather permitting, on September 29, 2023, Kenmore Construction will switch traffic on Old Rockside Road  Bridge over the Cuyahoga River within the limits of Independence and Valley View.
  • Traffic will now travel on the newly constructed permanent roadway just to the south of the temporary roadway.
  • Traffic will remain in this pattern permanently and the adjacent properties will be restored to their original condition.
  • Maintenance of traffic Phasing Plan - Phase 3

August 22, 2023

  • A concrete deck for the permanent bridge has been placed.
  • Additional work on the parapets, sidewalk, and curbs to come in the upcoming weeks.
  • Traffic is still maintained via the temporary bridge.

June 9, 2023

  • Contractor has been working on completing concrete work for permanent substructures.
  • The contractor has placed permanent rock channel protection stone and is working on placing revetment system blocks along the east and west riverbanks.
  • Bridge beam delivery and erection of beams is scheduled for the end of June.
  • Old Rockside traffic is maintained via the temporary bridge.

April 18, 2023

  • The temporary bridge is currently open to traffic over the Cuyahoga River.
  • Pile driving work is currently taking place for the piers/abutments of the proposed permanent structure.
  • Access to the nearby businesses, parks, driveways, and roadways are all currently open and available for public use.

 

Page Title

icon of house

Property Search

Search property information and more.
icon of house

Court Dockets

Case Records Search System.
icon of file

Recorded Docs.

Cuyahoga County official records search.
icon of people

Social Services

Find benefits and services for County residents.