Construction Updates

Chagrin River Road - Removal of Bridge over Deer Lick Creek
CONTACTS
Contractor: Northeast OH Trenching Services, Inc.
(216) 440-1768
County: Ryan Maver 216-533-0521
Brian Vigh 216-301-9010
DATES
Start Date: 06-01-2024
Notice To Proceed Date: 06-01-2024
Completion Date:
Scheduled Completion Date: 11-30-2024
Anticipated Completion Date: 04-30-2025
AMOUNTS
Project Amount($):
Contract Award Amount($): 1,574,530.45
Estimated Cost To Completion($): $607,633.31
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

January 2, 2024

Current Zone

  • Chagrin River Road is close between Miles Rd., and Sulphur Springs.
  • Sulphur Springs is now open from Chagrin River Rd. to Miles Rd., as part of the project’s new roadway extension.
  • The intersection of Miles Rd., and Sulphur Springs is being controlled by temporary traffic signals.
  •  

    Current Work:

  • The Chagrin River Bridge Demolition has begun and is almost completed.
  • The bridge deck, piers, and abutments have been removed.
  • Work will continue to restore the area once demolition is complete.

 

December 2, 2024

Current Zone

  • Chagrin River Road is close between Miles Rd., and Sulphur Springs.
  • Sulphur Springs is now open from Chagrin River Rd. to Miles Rd., as part of the project’s new roadway extension.
  • The intersection of Miles Rd., and Sulphur Springs is being controlled by temporary traffic signals.

     

    Current Work:

  • No work was performed in the month of November 2024. Awaiting approval for the Chagrin River Bridge demolition.

November 5, 2024

Current Zone

  • Chagrin River Road is close between Miles Rd., and Sulphur Springs.
  • Sulphur Springs is now open from Chagrin River Rd. to Miles Rd., as part of the project’s new roadway extension.
  • The intersection of Miles Rd., and Sulphur Springs is being controlled by temporary traffic signals.

     

    Current Work:

  • Asphalt and striping were completed to open the new Sulphur Springs extension to Miles Rd.
  • Next phase of the project is the demolition of the Chagrin River Road Bridge.

Chagrin River Road Construction    Chagrin River Road Construction

 

October 4, 2024

Current Zone

  • Two Temporary Fully Actuated Traffic Signals on Miles Rd. and Three Temporary Fully Actuated Traffic Signals on Chagrin River Rd and Sulphur Springs Dr.
  • Phase 2A MOT in place. This includes closure of EB lane on Miles Rd where one way traffic is maintained on WB lane. SB lane on Chagrin Rd is closed and one way traffic is maintained on NB lane. Sulphur Springs Drive is closed for 75 days.

     

    Current Work:

  • Contractor closed Sulphur Springs Drive per 2A phase of the project for 75 allowable days. Sulphur Springs road has been removed for re-alignment. Current work is being done to compact the subgrade, perform cement stabilization, and pave asphalt road base.

     

 

 

September 3, 2024

Current Zone

  • Two temporary fully actuated traffic Signals on Miles Road and three temporary fully actuated traffic signals on Chagrin River Road and Sulphur Springs Drive.
  • Phase 1A MOT in place. This includes closure of WB lane on Miles Road where one way traffic is maintained on EB lane. NB lane on Chagrin Road. is closed and one way traffic is maintained on SB lane.

Current Work:

  • The contractor is working on building the Sulphur Springs extension to Miles Road. This included building subgrade, performing cement stabilization, placing stone and asphalt roadway.
  • New traffic support foundations for the new Miles Road and Sulphur Intersection have been installed.

Chagrin River Road construction    Chagrin River Road construction    Chagrin River Road construction

August 2, 2024

Current Zone

  • Two temporary fully actuated traffic Signals on Miles Road and three temporary fully actuated traffic signals on Chagrin River Road and Sulphur Springs Drive.
  • Phase 1A MOT in place. This includes closure of WB lane on Miles Road where one way traffic is maintained on EB lane. NB lane on Chagrin Road. is closed and one way traffic is maintained on SB lane. < /li>

Current Work:

  • The contractor is working on installing permanent signals on Miles Road for the new intersection placement. They also brought in fill dirt to begin spreading for the new Sulphur Drive extension.

Chagrin River Road construction    Chagrin River Road construction    Chagrin River Road construction



  
How could we make it better? Leaving an email can assist us in troubleshooting the issue.
  
Thank you for your feedback
Your feedback means a lot to us. We use it to improve the experience of all of our users.