DATES
Start Date: 04-01-2024
Notice To Proceed Date: 04-01-2024
Completion Date:
Scheduled Completion Date: 11-01-2024
Anticipated Completion Date: 11-01-2024
AMOUNTS
Project Amount($):
Contract Award Amount($): 1,998,321.23
Estimated Cost To Completion($):
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

May 2, 2024

Progress:

  • Eastbound concrete lane removed.
  • Eastbound curb removal
  • Removal of underdrain
  • Eastbound concrete Lane replaced.
  • Eastbound curb replaced.
  • New under drain installation.

Expected in the upcoming weeks:

  • Concrete pavement removal at Fair Oaks and First Place.
  • New under drain installation.