Construction Updates

Grant Avenue - From E. 49th Street to 71st Street
CONTACTS
Contractor: Vandra Brothers Construction

County: Ryan Maver
Pat Lynch (440) 804-6900
DATES
Start Date: 06-01-2024
Notice To Proceed Date: 06-01-2024
Completion Date:
Scheduled Completion Date: 11-30-2024
Anticipated Completion Date: 11-30-2024
AMOUNTS
Project Amount($):
Contract Award Amount($): 1,580,963.85
Estimated Cost To Completion($): $750,000.00
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

September 3, 2024

  • Surface course asphalt complete.
  • Permanent pavement markings and detector loops complete for traffic control.
  • Detour removed and road open to two-way traffic.
  • Project substantially completed.

August 1, 2024

  • Eastbound lane milled, pavement repairs completed, intermediate course asphalt placed.
  • Westbound lane milled and intermediate course asphalt placed with pavement repairs, casting adjustments, and curb ramp placement in progress.

July 3, 2024

  • Eastbound lane milled, pavement repairs completed, intermediate course asphalt placed.
  • Casting adjustments in progress.

Grant Avenue Construction    Grant Avenue Construction



  
How could we make it better?
   Please leave a comment before submitting.
Thank you for your feedback
Your feedback means a lot to us. We use it to improve the experience of all of our users.